Terminate Batches
Batching for each channel set for batch will automatically terminate when
each batch channel PV Total has reached or exceeded its programmed SP
Batch setpoint.
You can terminate any channels that continue with batching remaining in
process by first returning to the home screen, then pressing the STOP key
once. Note that the ‘B’ control indicators on the home screen stop blinking,
indicating that all batch processes are stopped. Pressing the START key
three times will always reset all batch totals to zero before starting the
process.
3-6-4 Blend Control
Blending is a continuous process that, when started, causes slave SP
Rates to be a proportion of the actual rate being delivered by the master
rate.
NOTE: Blend parameters are saved when power is lost, allowing blending to continue
after power is restored unless Pwr SP Clear is selected to be ON. Refer to "3-5-3
Global Control Services" on p. 3-14.
Select a master channel and set its delivery SP Rate. One or more slave
channels are then selected, and the process is started from the home
screen. Once started, blending will continue and may ONLY be terminated