Specifications subject to change without notice. © 2013 Brivis Climate Systems Pty Ltd
24
7.4 Commissioning Sheet
Installer; please complete all sections of this form.
SYSTEM INFORMATION
PRE START-UP
(Please tick boxes below as each item is completed).
VERIFY THAT ALL PACKAGING MATERIALS HAVE BEEN REMOVED FROM UNIT.
REMOVE ALL SHIPPING HOLDDOWN BOLTS AND BRACKETS, AS PER INSTALLATION INSTRUCTIONS.
CHECK THAT CONDENSATE CONNECTION IS INSTALLED, AS PER INSTALLATION INSTRUCTIONS.
CHECK ALL ELECTRICAL CONNECTIONS AND TERMINALS FOR TIGHTNESS.
CHECK THAT INDOOR RETURN AIR FILTER IS CLEAN AND IN PLACE.
VERIFY THAT UNIT INSTALLATION IS LEVEL.
CHECK FANS FOR ALIGNMENT AND NOISE.
OPERATION CHARACTERISTICS
(Please record the following data after at least 20 minutes running time).
Suction Pressure
kPa
Suction Line Temperature
o
C
Discharge Pressure
kPa
Liquid Line Temperature
o
C
Superheat
K
Sub-cooling
K
Compressor Amps (L1)
A
Compressor Amps (L2 for 3 phase)
A
Compressor Amps (L3 for 3 phase)
A
Indoor coil Air On (Return) Temperature
o
C DB
Indoor coil Air Off (Supply) Temperature
o
C DB
Outdoor air Temperature (Ambient)
o
C DB
Length of liquid line
m
Length of suction line
m
Liquid line Diameter
mm
Suction line Diameter
mm
Extra refrigerant quantity charged (if any)
kg
Supply voltage
V
Actual voltage
V
ICE MODEL
(Outdoor Unit)
SERIAL No.
(Outdoor Unit)
ICE MODEL
(Indoor Unit)
SERIAL No.
(Indoor Unit)
HEATER MODEL
HEATER SERIAL No.
INSTALLED BY/ DATE