Page 30
Figure 15. DHW Piping - Two Heaters, Two Vertical Tanks
7.7 Condensate Drain Trap
A condensate drain trap is included with the unit
and is designed to drain the unit of condensate.
See Figure 2 on page 7. The vent condensate
should be drained through a drain tee located in
the vent line. This will help prevent excessive
condensate from entering the unit at the vent.
The condensate drain must be installed to
prevent the accumulation of condensate. When
a condensate pump is not used, the tubing must
continuously slope downward toward the drain with
no spiraling.
7.6 Water Flow
6HH6HFWLRQIRUZDWHUÀRZDQGKHDGUHTXLUHPHQWV
1RWH7KHKHDGORVVIRUWKHSLSLQJ¿WWLQJVDQG
accessories must be calculated and added to the heater
head loss to get the total required pump head. An
XQGHUVL]HGSXPSZLOOUHVXOWLQLQVXI¿FLHQWÀRZ7KLV
can result in scale buildup and failure of the heat
exchanger.
Connect a 3/4” PVC pipe between the drain
FRQQHFWLRQDQGDÀRRUGUDLQRUFRQGHQVDWHSXPSLID
ÀRRUGUDLQLVQRWDFFHVVLEOH
Consult local codes for the disposal method.
A condensate neutralizer is not included with the unit
and yet is almost always used. It is advised that the
unit be installed on a raised 4” concrete platform so
WKDWWKHUHLVVXI¿FLHQWHOHYDWLRQIRUWKHFRQGHQVDWH
neutralizer below the included condensate trap. See
Figure 8 on page 23
Caution
Condensate is mildly acidic (pH
=
5), and
PD\KDUPVRPHÀRRUGUDLQVDQGRUSLSHV
particularly those that are metal. Ensure that
the drain, drainpipe, and anything that will come
in contact with the condensate can withstand
the acidity, or neutralize the condensate before
disposal.
Damage caused by failure to
install a neutralizer kit or to adequately treat
condensate will not be the manufacturer’s
responsibility.
NOTES:
1. Optional CWMU & recirculation line location.
2. Locate NTV DHW sensor or remote aquastat well in lower 1/3 of tank.
3. Back Flow Preventer may be required. Check local codes.
4. Thermal expansion tank may be required. Check local codes.
5. Factory mounted pumps are sized for a max pipe length of 30’ total, 6-90° elbows, full pipe size.
6. CAUTION: Pump sizing must be based upon water hardness at job site.
NOTE:
This drawing shows
suggested piping
FRQ¿JXUDWLRQDQGYDOYLQJ
Check with local codes and
ordinances for additional
requirements.
EXPANSION
TANK
Location of pump
.
Location of pump
.
Optional location for
COLD WATER SUPPLY
EXPANSION
TANK
BUILDING
RETURN
BALL VALVE
(TYPICAL)
Check valve
Check valve
Summary of Contents for Brute MagnaTech BMGH1600
Page 4: ......
Page 47: ...Page 43 Figure 24 High voltage wiring diagram Model 1600 208V Single Phase ...
Page 54: ...Page 50 8 12 Ladder Diagrams continued Figure 31 Model 1600 208V 1 Phase ladder diagram ...
Page 56: ...Page 52 8 12 Ladder Diagrams continued Figure 33 Model 2000 208V 1 Phase ladder diagram ...
Page 104: ...Page 100 1 13 12 4 3 5 13 2 15 DETAIL A 9 10 8 DETAIL Final Assembly ...