Header connection
6 720 613 057 (2006/04)
29
8
Header connection
Information on laying the header pipes can be found in
the complete station installation instructions.
The water connection to the header pipes is made using
the long flexible connection pipes. It is not permitted to
connect a fixed header pipe directly to the collector.
8.1
Venting through pressure filling
If venting of the solar heating system is carried out using
a pressure filling pump, no vent is required on the roof.
B
Push connection pipe (1000 mm, Fig. 33, Item 2)
onto the flow connection on the collector array and fix
in place using bracket (Fig. 33, Item 1).
B
Feed connection pipe together with the sensor cable
through the roof.
B
Connect header pipe to the compression fitting
(Fig. 33, Item 3).
Perform the same procedure with the return connection.
Fig. 32
Routing connection pipes under the roof
Item 1: Flow line
Item 2: Return line
63043973.04-1.SD
63043973.04-1.SD
1
2
i
USER NOTE
Feed the sensor cable together with the
flow line under the roof.
Fig. 33
Fitting flow line (with no vent on roof)
63043973.06-1.SD
63043973.06-1.SD
3
1
2
Summary of Contents for Worcester FKT Series