Transport, Installation and Connection
4-4
4.9
Installation
All installation and connection work may be carried out by
qualified and approved specialist staff only ! The legal
regulations as well as adjustment instructions of the plant
operator have to be observed!
2
4
5
3
1
1 Compact Flame Controller
2 Optical alignment device
3 Purge air flange
4 Heating insulator
5 Swivel mount
The mounting flange has slots for easy installation of the
compact flame controller housing. Tighten all four M5
bolts.
The sight tube connection has a G1" internal pipe thread.
The sight tube connection has a G1" internal pipe thread.
In order to ensure perfect flame monitoring, the correct
and low-vibration position of the sight tube relative to the
flame is a significant pre-requisite. For selective burner
monitoring, the device has to be installed in such a way
that the primary combustion zone in all load ranges is in-
side the visual angle of the compact flame controller. The
view axis should, if possible, intersect the first third of the
flame of the monitored burner. The extension of the view
axis must not intersect the first third of the flame of other
burners. Adjust the compact flame controller so that an
optimum view is obtained.
Summary of Contents for CFC 100
Page 2: ......
Page 11: ...General aspects 1 7 1 8 Declaration of conformity ...
Page 20: ...Safety 2 8 ...
Page 24: ...Technical data 3 4 3 5 Block diagram CFC100 ...
Page 36: ...Transport Installation and Connection 4 12 ...
Page 40: ......
Page 42: ...Operation of the Compact Flame Controller 6 2 ...
Page 46: ...Failures 8 2 ...