18
Robusta SC
5)
Remove any dust and small particles from
the drill holes using a brush and hand
pump. This will ensure perfect adhesion
between the resin for the ground anchor and
the concrete foundation.
6)
Place the chemical anchors according to the
supplier’s instructions. Resin drying times
must be observed.
4.3. Preparing of the installation levels:
1)
Screw the lower adjustment nuts onto their
ground anchors some 25mm above the
concrete and place the 3D washers onto the
nuts.
2)
Using a spirit level (see photo) adjust the
height of all 4 nuts so that they are horizontal
to one and other. The guiding post position
serves as a reference point for the installation
of the other main components (Roller
assembly, lock post and support roller).
3)
The nuts of each mounting position (rear
roller assembly and lock post) should be
perfectly horizontal and relative to another, so
that the horizontal and vertical positions for
the main support elements of the gate are
correctly aligned before the gate is lowered
onto the anchors.
Summary of Contents for R2000
Page 1: ...1 Robusta SC Cantilever sliding gates Robusta SC Installation Manual ...
Page 11: ...11 Robusta SC 4 1 1 Automatic version right opening ...
Page 12: ...12 Robusta SC 4 1 2 Automatic version left opening ...
Page 13: ...13 Robusta SC 4 1 3 Motorizable version right opening ...
Page 14: ...14 Robusta SC 4 1 4 Motorizable version left opening ...
Page 15: ...15 Robusta SC 4 1 5 Manuel version right opening ...
Page 16: ...16 Robusta SC 4 1 6 Manuel version left opening ...