2x4 Truss
1x6 Fascia
Plyclip
2.
Install a 22-1/2" long 2x4 block
between the center truss to
support the 1x6 fascia board.
Truss
Shingles
Air
Space
1.
Install 4x8 roof sheathing across the top of the roof. The bottom edge of sheathing should
extend past the end of the 2x4 truss to receive the 1x6 fascia. Secure sheathing with 7d sinkers.
Space nails 12" apart. Note: If you are installing optional ridge vent allow a 1" space at the
peak of the trusses for air flow. See detail below.
Step 11
Install Roof Sheathing & Soffit
3.
Cut leftover siding and install as soffit under the truss overhang.
4.
Install 1x6 fascia over the ends of the trusses, flush with the top of the roof sheathing.
The 1x6 should extend 3/4" beyond the siding on the side walls to receive the 1x4
gable trim installed next. Use 8d galv. nails.
4x8 Sheathing
5.
Install a full sheet at the lower portion of the
rear of the building. Install 2' wide roof sheathing
at the top rear of the building. Insert a plyclip
where the rear roof sheathing butts together
between the trusses.