Microseparator™ Coolant Systems Transport, Installation, & Initial Startup
M000005_A - V Twin Ultra Transport & Installation 5.2-EN TM
21/78
Installation Requirements- Microseparator™ Main Systems
10.4
Overview
10.4.1
Floor Requirements
•
The installation area for the machine should be self-supporting
and level.
•
The centrifuge component of the system must be lagged to the
floor using appropriate concrete anchor bolts.
•
When selecting the installation area, avoid placing the machine on
a step, drain, or similar.
•
The load bearing capacity of the floor must be at least 800 kg/m².
10.4.2
Ambient Conditions
No specific requirement. Equipment is designed for indoor installation. If
equipment is to be placed outside, contact Bazell Technologies in advance
of order.
10.4.3
Electromagnetic Influence
Interference from other electric installations (high frequency) must be
avoided. The main system electrical control panel contains one variable
frequency drive.
10.4.4
Utility Connections
Refer to the following Connection Schedule diagrams for all utility
requirements and connection points and refer to
Requirements page 22
and
11.1 belowMicroseparator™ Coolant System
11.2 Microseparator™ Coolant System - HC page
Note: The machines have been preset to the voltage specified on the
rating plate prior to delivery and have been delivered without a cable for
connection to the mains supply.
10.4.5
Piping Installation Diagrams
See the “Piping Installation” diagrams provided with the equipment.
Note: Piping Installation diagrams are specific to the component groups
specified on your order.