Microseparator™ Coolant Systems Transport, Installation, & Initial Startup
M000005_A - V Twin Ultra Transport & Installation 5.2-EN TM
75/78
22.3
Shut Down
Press the SEPARATOR button and then STOP. This will start a series of
actions.
1.
Machine will go through a complete cleaning cycle.
2.
Once the cleaning cycle is complete, the machine will now restart to
check for any imbalance in the rotor indicating an incomplete rotor
cleaning.
3.
If the rotor cleaning was incomplete, vibration will be present and
force the machine into another cleaning cycle. This cycle will repeat
until vibration is no longer present.
4.
Machine will shut down until started again.
5.
Power off.
6.
Turn off power to The Chip Separator Transfer Tanks.
Caution: Do not use Emergency Stop or turn off main breaker to shut
down main system during normal shut down procedure. The
Microseparator™ should always go through a cleaning cycle before
shutting down for maintenance or any lengthy period of time.
22.4
Screen Box Operation and Service
At the top of the main tank sits a
screen box through which coolant
and debris is constantly pumped
while the system is powered on.
The screen should be cleaned daily
using a soft bristle brush such as a
radiator brush or paint brush.
Clean w ith soft bristle brushes
only (brass, horsehair, plastic,
etc.) as the edges of the screen
w ill become dull and depreciate
system performance. Operating
properly, you should see debris
accumulating on the screen
surface and being w ashed dow n
the face of the screen into the
dirty side of the tank.
Figure 49 – Screen Box Cleaning