PD-TaD 80
Connecting the system
822-188-3
39 / 74
No.
Cable
Step
1
Protective earthing
cable of the VLF HV
generator
Earth the VLF HV generator.
Further information: User manual for the respective VLF HV generator
2
Protective earthing
cable of PD-TaD 80
(flat copper strip)
Connect the PD-TaD 80 to the station earth (close to the test object cable
screen).
Further information: Chapter
Earth system
(on page 34)
On the VLF HV generator:
–
–
If present, connect the external emergency off unit to the VLF HV generator
(
port).
If you are not using an external emergency off unit, ensure that a jumper
plug is inserted into the
port on the VLF HV generator.
3
Connection cable
C19
– C20G
Connect the VLF HV generator (mains supply) to the Power Box (port
depends on the connection cable).
On the laptop:
4
USB cable
Use the USB cable to connect the laptop to the VLF HV generator.
5
Ethernet cable
Use the supplied Ethernet cable to connect the laptop to the Power Box
(
Laptop
port).
–
–
If you do not want to run the laptop off its battery, connect the laptop to the
Power Box to establish a power supply. To do so, use the connection cable
with the C14G plug.
At the PD-TaD 80:
6
PoE cable
Connect the PoE cable:
to the Power Box (
PD Detector
port) and
to PD-TaD 80 (
Power Box
port)
This is used for power supply and data transmission at the same time.
7
–
Connect the HF filter to the
HV IN
port.
Further information: Chapter
Connecting the HF filter to the PD-TaD 80
(on
8
HV connection cable of
the VLF HV generator
Connect the screen of the HV connection cable to the
Screen (HV Cable)
port.
9
See above
Connect the HV connection cable to the HF filter at the
HV IN
port.
Further information: Chapter
Connecting the HF filter to the PD-TaD 80
(on
10
Short-circuit cable of
PD-TaD 80
On the PD-TaD 80, remove the short-circuit cable from ports
HV IN
and
HV OUT
.
At the far end of the test object:
11
–
Clean the cable termination of the phase to be tested carefully.
12
–
Attach the anti-corona hoods of the anti-corona protection device to the
cable termination of the phase to be tested.