4/
Preparation for operation
18/52
1686-000 GB/2021-03
4 Preparation for operation
4.1 Requirements for setup location
The setup location for the ultrasonic bath must meet the following
conditions:
• The setup surface must be horizontal, solid and dry.
• The load-bearing capacity must be sufficient for the ultrasonic
bath with the sonication fluid. For weight and operating volume,
see chapter
8 Technical data
.
• Sufficient ventilation must be guaranteed. The supply of air
under the bottom of the ultrasonic bath may not be hindered by
objects. If a soundproof box is used, it must also guarantee suf-
ficient ventilation.
• A water connection for filling the ultrasonic bath should be
located nearby. A basin must be available for draining or pouring
out the sonication fluid.
4.2 Fitting ball valve
Concerns ultrasonic baths from DT 102 H / DT 102 H-RC.
Fit the supplied ball valve, the hose grommet and the hose as
described in the assembly instructions included with the ball valve.