SUPPLY LINE
The figure below shows the gas supply line block diagram.
Install a manual shut-off valve and an anti-vibration joint upstream of
the gas valve, as shown in the diagram.
If the gas train is equipped with a pressure regulation device not
integrated in a monoblock valve, follow the instructions below to
install the accessories on the gas pipe near the burner:
•
To avoid high pressure drops upon ignition, there should be a 1.5/2
m long pipe section between the pressure reducer or stabiliser
installation point and the burner. The tube diameter should be
equal to or greater than the burner attachment union.
To ensure optimal operation of the pressure regulator, it should be
applied to the horizontal pipe after the filter.
The gas pressure regulator must be adjusted when it is working at the
maximum output actually used by the burner.
The delivery pressure must be adjusted to a level slightly below the
maximum obtainable.
BURNER CONNECTION TO THE BOILER
HEAD UNIT ASSEMBLY
•
Position the insulating gasket (13) on the sleeve, by inserting the
cord (2) between the flange and the gasket.
•
Adjust the position of the coupling flange (19) by loosening the
screws (6) so that the burner head enters the furnace to the extent
recommended by the generator manufacturer.
•
Fasten the burner to the boiler (1) by means of the stud bolts,
washers and the nuts provided (7).
DANGER / ATTENTION
Seal the space between the burner sleeve and the hold on
the refractory material inside the boiler door completely with
suitable material.
0002935610
19
2
1
7
6
13
11 / 34
0006160178_202211
ENGLISH
Summary of Contents for TBG 45 P
Page 2: ......
Page 33: ...SCHEMI ELETTRICI 31 34 0006160178_202211 ITALIANO...
Page 34: ...32 34 0006160178_202211 ITALIANO...
Page 36: ...34 34 0006160178_202211 ITALIANO...
Page 67: ...WIRING DIAGRAMS 31 34 0006160178_202211 ENGLISH...
Page 68: ...32 34 0006160178_202211 ENGLISH...
Page 70: ...34 34 0006160178_202211 ENGLISH...
Page 71: ......