2-20 Installation
Pre-Operation Checks
Check of Electrical Items
After completing all the installation steps and before applying line
power to the system, carefully check the following items:
1.
Verify AC line voltage at source matches control rating.
2.
Inspect all power terminations for workmanship and
tightness.
3.
Verify control and motor are grounded to each other and the
control is connected to earth ground.
4.
Check incoming signal wiring for accuracy.
Be certain all brake coils, contactors, and relay coils have
noise suppression. This should be an R-C filter for AC coils
and reverse polarity diodes for DC coils. MOV type
transient suppression is not adequate.
WARNING: MAKE SURE THAT UNEXPECTED
OPERATION OF THE MOTOR SHAFT
DURING START-UP WILL NOT CAUSE
INJURY TO PERSONNEL OR DAMAGE TO
EQUIPMENT.
Check of Motors/Couplings
Verify freedom of motion for all motor shafts and that all motor
couplings are tight without backlash.
Verify the holding brakes, if any, are properly adjusted to fully
release and set to the desired torque value.
Summary of Contents for ID10101-E
Page 1: ...Series 10 Inverter Control Installation and Operating Manual 2 00 MN710 AC INVERTER ...
Page 13: ...1 8 General Information ...
Page 35: ...2 22 Installation ...
Page 67: ...4 6 Troubleshooting ...
Page 68: ...Section 5 Illustrations Illustrations 5 1 ...
Page 69: ...5 2 Illustrations ...
Page 70: ...Illustrations 5 3 3 5 HP NEMA 1 230 460VAC ...
Page 71: ...5 4 Illustrations ...