3-8 Receiving & Installation
MN2408
Example: Determining Pipe Size for LPG
A generator has a 16Hp engine 60 feet from the supply.
Determine the supply pipe size for Natural Gas fuel.
16 x 10,000 = 160,000 BTU’s / per hour for proper operation.
160, 000
2, 516
+
63.5 cubic feet per hour.
From Table 3-6, a 60 foot run requires a minimum 1” pipe at full engine load.
LP Gas Connections
(vapor withdrawal only)
The LPG connections should only be made if your generator is setup to run on LPG. If it is setup
to run on Natural Gas, contact your Baldor representative and do not continue with installation.
The incoming pressure must be 11 inches water column (6 oz. pressure).
Table 3-6 LP Gas Flow Rate (Cubic Feet per Hour) per Pipe Length
Pipe
Length
Iron Pipe Size
Length
(Feet)
1
/
2
″
3
/
4
″
1
″
1–
1
/
4
″
1–
1
/
2
″
2
″
2–
1
/
2
″
3
″
4
″
6
″
8
″
15
48
109
218
475
772
1570
2437
4115
8786
24497
50007
30
33
76
153
339
538
1127
1741
2975
6140
17325
35353
45
27
63
126
275
443
934
1456
2469
5001
14781
28865
60
24
54
110
241
386
817
1266
2184
4304
12236
25004
75
49
98
218
345
709
1108
1899
3798
10957
22345
90
44
89
196
310
633
987
1709
3482
10001
20414
105
41
83
180
285
582
905
1551
3228
9254
18895
120
76
171
266
544
848
1456
3038
8659
17673
150
69
153
241
494
772
1323
2754
7748
15825
180
63
142
222
456
709
1234
2532
7064
14432
210
58
130
202
418
652
1127
2342
6439
13356
240
120
190
393
614
1063
2209
6077
12405
270
113
180
367
576
1000
2057
5697
11780
300
108
171
345
544
943
1899
5381
11179
Note: Almost all operation problems are related to the installation techniques used.
Do Not guess, be sure pipe size is adequate for required flow rate.
1.
Connect the proper size gas pipe at the input to the LP Gas regulator. Connect the
LPG pipe line shown in Figure 3-3 using the correct size pipe for the required flow rate
and length of pipe. Refer to Table 3-6 for pipe size. Be certain that all connections are
sealed and no leaks are present. The installer must ensure that all gas connections
comply with all building codes.
2.
Verify Fuel Supply Pressure
Prior to initial operation of generator, verify that fuel system pressure is 11
″
Water
Column (6 oz. pressure) and fuel pipe sizes comply with Table 3-6.
3.
Proceed to Electrical Connections.
Summary of Contents for GLC30
Page 12: ...2 2 General Information MN2408...
Page 32: ...2 22 General Information MN2408...
Page 42: ...3 10 Receiving Installation MN2408 Figure 3 4 Three Phase WYE and DELTA Connections...
Page 52: ...4 6 Operation MN2408 Figure 4 3 Engine Controller Inputs Outputs...
Page 64: ...4 18 Operation MN2408 Figure 4 4 Configuration Data Sheet j j j j j j j j j...
Page 86: ...A 10 Series GLC MN2408 Figure A 2 Customer Interface Connection Diagram MEC20 MEC2...
Page 87: ...Series GLC A 11 MN2408 Figure A 3 Customer Interface w o Breaker Power Connection Diagram...
Page 88: ...A 12 Series GLC MN2408 Figure A 4 Single Phase w o Breaker Connection Diagram...
Page 89: ...Series GLC A 13 MN2408 Figure A 5 Single Phase One Breaker Connection Diagram...
Page 90: ...A 14 Series GLC MN2408 Figure A 6 Single Phase Two Breaker Connection Diagram...
Page 95: ...Series GLC A 19 MN2408 Figure A 11 Three Phase Connection Diagram...
Page 96: ...A 20 Series GLC MN2408 Figure A 12 Three Phase Connection Diagram with PMG...
Page 97: ...Series GLC A 21 MN2408 Figure A 13 Three Phase Connection Diagram Wire 1 0 and larger...
Page 104: ...A 28 Series GLC MN2408 Figure A 20 Control Box Connections with MEC2 Controller...
Page 105: ...Series GLC A 29 MN2408 Figure A 21 Engine Wiring Woodward 4 3L GM...
Page 106: ...A 30 Series GLC MN2408 Figure A 22 Engine Wiring Woodward 5 7L GM...
Page 107: ...Series GLC A 31 MN2408 Figure A 23 Engine Wiring Woodward 8 1L GM...
Page 108: ...A 32 Series GLC MN2408...