Operation 4‐15
MN2408
5.
When the cool down time delay period expires (typically 5 minutes), the controllers
RUN output will be immediately terminated which will initiate the engine to stop.
Automatic Fault Shutdown
When a fault circuit is programmed as a SHUTDOWN, the engine will immediately stop when the
fault is activated. A specific shutdown fault can be programmed with a definite time transient
delay period that must expire before the shutdown is activated. The stop sequence will cause the
controllers RUN output to be immediately terminated which will cause the engine to stop. This
will prevent subsequent operation of the generator set. The Run/Stop/Auto selector switch on the
operator control panel must be momentarily placed in the “Stop” position to reset the fault.
Automatic Mains Failure (AMF)
Figure 4‐14 Auto Mains Failure (AMF) Connections
Transfer
Switch
Summary of Contents for GLC10
Page 12: ...2 2 General Information MN2408...
Page 24: ...2 14 General Information MN2408...
Page 40: ...3 16 Receiving Installation MN2408...
Page 58: ...4 18 Operation MN2408 Figure 4 15 Engine Controller Inputs Outputs...
Page 70: ...4 30 Operation MN2408 Figure 4 16 Configuration Data Sheet j j j j j j j j j...
Page 74: ...4 34 Operation MN2408...
Page 88: ...A 10 Series GLC MN2408...
Page 90: ...B 2 Series GLC MN2408 Figure B 11 Customer Interface Connection Diagram MEC20 MEC2...
Page 91: ...Series GLC B 3 MN2408 Figure B 12 Customer Interface w o Breaker Power Connection Diagram...
Page 92: ...B 4 Series GLC MN2408 Figure B 13 Single Phase w o Breaker Connection Diagram...
Page 93: ...Series GLC B 5 MN2408 Figure B 14 Single Phase One Breaker Connection Diagram...
Page 94: ...B 6 Series GLC MN2408 Figure B 15 Single Phase Two Breaker Connection Diagram...
Page 99: ...Series GLC B 11 MN2408 Figure B 20 Three Phase Connection Diagram...
Page 100: ...B 12 Series GLC MN2408 Figure B 21 Three Phase Connection Diagram with PMG...
Page 101: ...Series GLC B 13 MN2408 Figure B 22 Three Phase Connection Diagram Wire 1 0 and larger...
Page 106: ...B 18 Series GLC MN2408 Figure B 27 Control Box Connections with MEC20 Controller...
Page 107: ...Series GLC B 19 MN2408 Figure B 28 Control Box Connections with MEC20 Controller Governor...
Page 108: ...B 20 Series GLC MN2408 Figure B 29 Control Box Connections with MEC2 Controller...
Page 109: ...Series GLC B 21 MN2408 Figure B 30 Engine Wiring Woodward 4 3L GM...
Page 110: ...B 22 Series GLC MN2408 Figure B 31 Engine Wiring Woodward 5 7L GM...
Page 111: ...Series GLC B 23 MN2408 Figure B 32 Engine Wiring Woodward 8 1L GM...
Page 112: ...B 24 Series GLC MN2408...
Page 113: ...Baldor District Offices...