37
29.04.2013 TB-b bta_bj_vogue_wave_engl_29042013.indd
Final assembly of the BADU
®
Jet wave
1) After installing the jet housing.
2) Glue in the cable protection hose and the air line hose. (Fig. 9)
3) Place the nozzle housing (102.1) onto the jet housing (1).
4) Insert the pneumatic hoses and cables of the floodlight through the protective hose (14) and seal using
the screwed cable gland (20).
5) Use clamp (8) to fasten the air hose to the factory-mounted air regulator (21).
6) Fasten the nozzle housing (102.1) to the jet housing (1) using the 4 self-tapping screws (95).
(Fig. 16)
Tighten the self-tapping screws to just hand tight. Do not use force!
7) Guide the pneumatic hoses through the openings in the trim (93) (light ON-OFF left;
pump ON-OFF right) and fasten to the corresponding buttons using the hose clamps (46).
(Fig. 17)
8) Fasten trim (93) to the nozzle housing using the four screws (113).
Tighten the self-tapping screws to just hand tight. Do not use force!
Insert the two pneumatic buttons through the trim (93) in the nozzle housing and turn clockwise
to lock. (Fig. 18)
9) Mount the cap for the air regulator. (Fig. 19)
10) Connect the jet pump (92) with the half fitting (98, 99, 100), the rubber bracket (79) and the
corresponding clamps (75) on the suction and pressure side to the jet housing.
11) Connect the pump motor according to the wiring diagram.
Ensure the correct direction of rotation with the three-phase motor!
12) Switching on and off from the pool using pneumatic buttons:
Pump ON-OFF (38/1) - right button
Light ON-OFF (38/2) - left button
13) The air regulator (21) can be used to admit air to the nozzle.
Please observe!
The jet housing is made
from ABS. If the suction
and pressure connections
are glued in-situ, allow for
a curing time of at least
12 hours!