9.9 Fitting the boiler onto the boiler frame
After the pipe work of gas, heating installation and DHW installation has been fitted to the boiler frame, the
boiler can be placed on the boilerframe.
Before hanging the boiler to the boiler frame remove first the cover of the boiler first. The cover is also the air
cabinet and is attached to the boiler case with 2 fasteners (A and B) (see figure 8.a).
Always refit and turn the 2 screws tight in the fasteners A and B after replacing the cover.
Remove furthermore the 6 plastic caps from the boiler connections.
When removing the plastic sealing caps from the pipes, contaminated testing water may be released.
Lift the boiler only by the boilers case.
Lifting and carrying precautions:
- Lift only a manageable weight, or ask for help.
- When lifting the boiler, bend the knees, and keep the back straight and feet apart.
- Do not lift and twist at the same time.
- Lift and carry the boiler close to the body.
- Wear protective clothing and gloves to protect from any sharp edges.
1. Press all connection underneath the boiler upwards
2. Put on each valve and the elbow fitting a fibre washer (supplied)
3 and 4. Take the boiler and hang it from approx. 50mm higher than the boiler frame vertical downwards on
the boiler frame so the fittings will be axial approached.
± 50mm
± 50mm
3
2
4
Figure 9.9.a
Figure 9.9.b
Bottom of
boiler
Jig nuts
1
2
Place mains
water filter in
cold water inlet