5.2
ELECTRICAL INSTALLATION
This procedure assumes the physical installation of the converter has been completed.
It is the installer’s responsibility to provide input service over-current protection and disconnect
means.
It is recommended that connection be made to the distribution bus through a manually operated
disconnect device such as a molded case switch or circuit breaker (rated for the total system
amperage) to ease disconnection and provide a safe servicing environment in the event of
converter failure.
Follow the table below when considering shore power input cabling.
MAXIMUM CURRENTS UNDER LOW-LINE CONDITIONS:
Model
AC100Q-3
Input Current@ Three Phase, 170-520V
155A
MAXIMUM OUTPUT CURRENTS: Refer to Table 1, page 11
All power wiring requires the removal of the front panel and the cable access cover (cabinet
bottom). Drill or punch appropriate holes for the selected strain reliefs. Re-install the front
panel using the removed hardware. Place the disconnect switch in the OFF position.
Summary of Contents for AC100Q-3
Page 15: ...AC100Q 3 Operations Manual 15 5 1 MECHANICAL INSTALLATION cont FIGURE 2 MECHANICAL OUTLINE ...
Page 16: ...AC100Q 3 Operations Manual 16 5 1 MECHANICAL INSTALLATION cont FIGURE 3 MECHANICAL OUTLINE ...
Page 38: ...AC100Q 3 Operations Manual 38 This page intentionally left blank ...
Page 55: ...AC100Q 3 Operations Manual 55 FIGURE 8 STATUS WORD BIT DEFINITIONS ...