5.2.2 Precautions
1.
High frequency hydraulic vibratory pile driver
s
should be carried by
the certified and skilled driver.
2.
The starting of the pile driver should be sped up from low gear to
high gear.
3.
Pay close attention to the indication of current and voltage on the
control box while working, in case of any abnormality, the machine shall
be stopped immediately for inspection.
4.
Free loading test should not surpass 5 min
utes
5.
While working please install the pile with
safety
wire in advance.
6.
When the hydraulic hoses breaks, please stop work immediately,
adjust the pile
to prevent
it from
falling
over
or
dropping
, and turn off
the
engine of the hydraulic excavator.
7.
When driving or pulling piles, please do not exceed the maximum
clamp
load of the pile driver, which may damage the elastomer and
cause the pile driver to
slip
off
the pile
. (please note the maximum
clamp
load
of pile driver used)
8.
Never force driving or pulling.
9.
Please do not stand under the pile driver except for the operation of
connecting piles.
10.
When the pile driver is running, be sure to clamp the
tooth
block
tightly. And confirm that the hydraulic system is running normally.
11. Impact driving (vibrating with the clamps open) will damage the
equipment.
12.
When clamping the pile, there should not be any space between the
jaws and the pile.
P28
Summary of Contents for AT 75 B
Page 1: ...2021 Operation Manual Side Grip Vibro Hammer...
Page 10: ...1 1 2 3 4 5 6 7 8 9 10 P8...
Page 11: ...1 4 Specification 1 4 1 Product Dimensions P9 102 12 inches 51 49 inches 50 23 inches...
Page 15: ...P13...
Page 28: ...P26...