Analyzer Flush Mounting (Preferred Method)
Weld the 17.78 cm x 19.37 cm (7" x 7 5/8" ) mounting plate (P/N 70626SE) sup-
plied with the analyzer to the process wall over a 9.52 cm (3 3/4" ) diameter
hole as shown in Figure 2-6. Then bolt the analyzer to the mounting plate.
The flush mount method is preferred because it positions the analyzer as close
to the process as possible and minimizes the chances of the sample gas cool-
ing below its dewpoint.
Sensor bolted to mounting plate after
plate is welded to wall by customer.
Gasket (by Ametek)
Mounting plate supplied by Ametek
with 2 7/8"OD x 9"long nipple (7.30cm
x 22.86cm) welded to wall over 3 3/4"od
(9.52cm) hole by customer.
Process wall
Probe
SIDE VIEW
Single stud at
12 o'clock position
Proper orientation for
mounting plate to flange
Figure 2-6.
WDG-V Analyzer flush mount
(preferred).
Installation and Start-Up
|
2-13
Summary of Contents for WDG-V
Page 12: ...PN 9000 133 VE Rev U This page intentionally left blank xii Thermox WDG V VC VCM VM...
Page 60: ...PN 9000 133 VE Rev U Figure 2 16 RCU Connections 2 34 Thermox WDG V VC VCM VM...
Page 93: ...PN 9000 133 VE Rev U Figure 3 4 Thermocouple replacement Maintenance and Troubleshooting 3 19...
Page 97: ...PN 9000 133 VE Rev U Figure 3 6 Flow sensor replacement Maintenance and Troubleshooting 3 23...
Page 103: ...PN 9000 133 VE Rev U Figure 3 10 Sensor board removal Maintenance and Troubleshooting 3 29...
Page 124: ...PN 9000 133 VE Rev U This page intentionally left blank 4 10 Thermox WDG V VC VCM VM...