2-2
TM-F2OP-C1XN-01
Basic Setup Procedure
See Table 2-1 for a summary of the basic setup procedure and an overall
view of the subsections in Chapter 2. Use the procedure as a quick
reference if you are familiar with the installation requirements for the
power supply. If you want more information, each step in the procedure
refers to subsequent sections which contain more details. Execute each
step in the sequence given.
See Chapter 3 for instructions about front panel operation, OVP, OTP,
shutdown, and using multiple supplies. You will find remote
programming and monitoring described in Chapter 4.
Table 2-1
Basic Setup Procedure
Step # Description
Action
Reference
1
Inspection
Perform an initial physical inspection of
the supply.
“Inspection, Cleaning, and
Packaging” on page 2–3
2
Installation
Install the supply (bench or rack
mount), ensuring adequate ventilation.
“Location, Mounting, and
Ventilation” on page 2–4
3
Input Power
Connect AC input power.
4
Test
Perform functional tests for voltage
mode operation, current mode
operation, and front panel controls.
“Functional Tests” on page 2–9
5
Load
Connect the load.
“Load Connection” on page 2–12
6
Sensing
Connect sensing lines.
Summary of Contents for Sorensen XFR 100-28
Page 3: ...This page intentionally left blank ii...
Page 5: ...This page intentionally left blank iv...
Page 7: ...This page intentionally left blank vi...
Page 13: ...xii...
Page 15: ...xiv...
Page 25: ...1 10...
Page 67: ...3 18...
Page 73: ...Remote Operation 4 6 TM F2OP C1XN 01 Figure 4 1 Connecting Programming Sources to J2 Connector...
Page 75: ...4 8...
Page 87: ...5 12...