5. Initial Programming
223
Task
POU
Priority
Type
Default
value
Options
Event
MainTask
MainPrg
13
Cyclic
20 ms
-
CyclicTask00
CyclicPrg00
13
Cyclic
200 ms
-
CyclicTask01
CyclicPrg01
13
Cyclic
500 ms
-
ExternInterruptTask00
ExternInterruptPrg00
02
External
-
COM1_CTS
TimeInterruptTask00
TimeInterruptPrg00
01
Cyclic
20 ms
-
ExternInterruptTask01
ExternInterruptPrg01
11
External
-
COM1_DCD
TimeInterruptTask01
TimeInterruptPrg01
09
Cyclic
30 ms
-
FreeTask
FreePrg
31
Freewhe
eling
-
-
Table 5-4. Tasks in the Customized Profile
ATTENTION:
The suggested names for the POUs associated to the tasks are not consisted in any profile. They can
be replaced as long as they are also replaced in the tasks configurations.
New Project
As previously described, there are different types of project profiles, depending on the technical
knowledge of each user. This chapter describes the creation of a new project using the Single profile,
through the “Wizard” tool, which presents all configuration options from the user system.
From the File menu, create a new MasterTool Xtorm project. Then, select “New Project…” as shown
in Figure 5-1:
Figure 5-1. New Project