1. Disconnect the AC breaker.
2. Check the control power supply. If it is OK, return the power supply to find out the
reason.
3. Please record every detail related to the fault, so AlphaESS can analyse and solve the
fault. Any operation of equipment during a fault is strictly forbidden, please contact
Alpha as soon as possible.
4. As battery cells contains a little Oxygen inside and all cells have got explosion-proof
valves, explosion hardly happens.
5. When the indicator light on the battery shows a red fault, check the fault type through
the communication protocol, and contact our after-sales service personnel for advice.
Step 1:
Turn on the PV switch
Step 2:
Turn on the external grid switch.
Step 3:
If backup load is applied, turn on the external Backup switch.
Step 5:
Set the communication address and communication baud rate in the
communication setting interface. When the meter is used as Grid meter (DC, AC/Hybrid
system), the address is set to “005” . When it is used as the PV meter (AC/Hybrid
system), the address is set to “006” . The baud rate is set to 9600.
SYSTEM OPERATION
SYSTEM OPERATION
3.1 Switch On
SYSTEM OPERATION
03
When turning on the system, it is very important to follow the steps below to prevent
damage to the system.
WARNING: Please check the installation again before turning on the system.
NOTE:
the Backup switch is only used when a backup load is applied.
1
2
Step 4:
Open the outer shell of the cable box. Open the battery switch cover and turn on
the battery switch on the cable box.
Step 5:
Press power button on all the batteries until the indicator lights turn on.
Step 6:
Close the battery switch cover and the outer shell of the cable box.
3.2 Switch Off
Step 1:
Press the power button on all the batteries, till the lights turn off.
Step 2:
Open cable box outer shell, open the battery switch cover and turn off the
battery switch.
Step 3:
Turn off the external grid switch.
Step 4:
If backup load is applied, turn off the external backup switch.
Step 5:
Turn off the PV switch on the cable box.
Step 6:
Close the battery switch cover and the outer shell of cable box.
More information can be found in SMILE5-BAT user manual.
3.3 Emergency Procedure
When the SMILE5 energy storage system appears to be running abnormally, you can
turn off the grid-connected main switch that directly feeding the BESS, and turn off all
load switches within the BESS, turn off the battery switch at the same time. To prevent a
potentially fatal personal injury, if you want to repair or open the machine after the
power is switched off, please measure the voltage at the input terminals with a suitably
calibrated voltage tester.
Before working on this equipment, please confirm that there is no grid electric supply to
the BESS!
The upper cover plate cannot be opened until the DC-link capacitance inside the battery
modules discharges completely about 15 minutes later.
3.3.1 Emergency Handling Plan
37
38