3. Operation
3-3
3.2 Connecting Loads
Select a cable with sufficient diameter by considering the load capacity and the distance from the
generator to the load. Use terminals for connection and securely fasten them.
(See 2.4)
A180877
After checking phase number and voltage of the load,
make sure to connect them correctly.
---Terminal Size---
3 Phase output (L1,L2,L3,N)
M8
Ground terminal (GROUND)
M8
A180788
Install a load switch between the output terminal and
the load to switch on/off the load. Do not switch the
load on/off directly by the circuit-breaker of the
generator. It could cause damage to the
circuit-breaker.
Connect the connecting cable to the load so that the
output terminals should not touch each other.
W013
When removing or connecting a connecting cable for changing
load, be sure to switch OFF the circuit breaker, and then carry out
a work. The operator must keep the key during operation.
For a connecting cable to load, do not use a cable with damaged
sheath nor an inappropriate insulation cable to the voltage. Secure
connections between each cable terminal and
input/output terminal. Otherwise, it may be slackened during
operation and may cause a fire or an electric shock accident.
3 Phase output terminal
Ground terminal
(GROUND)
Load Switch
Summary of Contents for Maxi-Power MP25 T4F
Page 59: ...N o t f o r R e p r o d u c t i o n 59 7 Specifications 7 3 Unit mm A180871E units mm...
Page 63: ...N o t f o r R e p r o d u c t i o n 63 7 Specifications 7 7 7 5 Piping Diagram A180872E...
Page 66: ...N o t f o r R e p r o d u c t i o n 66 ALLMAND COM...