START-UP

Pre-Start Check List

Complete the following checks before starting the unit:

1.

Check the type of gas being supplied. Be sure it is the
same as listed on the unit nameplate.

2.

Make sure that the vent cover has been properly
installed.

For Your Safety Read Before Lighting

To Light Main Burners:

1.

Turn off electrical power to unit.

2.

Turn the thermostat to lowest setting.

3.

Turn the gas valve knob to the “ON” position (see Figure
7).

4.

Turn on electrical power to the unit.

5.

Set the room thermostat to the desired temperature.  (If
the thermostat “set” temperature is above room
temperature after the pre-purge time expires, main
burners will light.)

To Shut Down Main Burners:

1.

Turn off electrical power to unit.

2.

Turn the gas valve switch to the “OFF” position (see
Figure 7).

Post-Start Check List

After the entire control circuit has been energized and the
heating section is operating, make the following checks:

1.

Check for gas leaks, using soapy solution, in the unit
piping as well as the supply piping.

2.

Check for correct manifold gas pressures (see Manifold
Gas Pressure Adjustment Regulator sections).

3.

Check the supply gas pressure.  It must be within the
limits shown on the rating plate. Supply pressure should
be checked with all gas appliances in the building at full
fire. At no time should the standby gas pressure exceed
13" w.c., nor the operation pressure drop below 5" w.c.
for natural gas units or 11" w.c. for propane gas. If gas
pressure is outside these limits, contact the gas supplier
for corrective action.

4.

Adjust temperature rise to the range specified on the
rating plate.

Furnace is equipped with a direct ignition control. Do not
attempt to manually light the burners.

 CAUTION

Typical Wiring Connections

Figure 7

Gas Valve

Figure 7

Gas Control Switch

 

 

 

Regulator
Adjustment
(Under Cap)

Summary of Contents for 506271-01

Page 1: ...also be followed Failure to do so may result in equipment damage personal injury and improper performance of the unit WARNING The installation of the furnace wiring warm air ducts venting etc must con...

Page 2: ...from water 2 Condenser coils must have an unlimited supply of air 3 For ground level installation use a level prefabricated pad or use a level concrete slab Do not tie the slab to the building founda...

Page 3: ...r shrubs to obstruct condenser air discharge outlet combustion air inlet or vent outlet Before lifting a unit make sure that the weight is distributed equally on the cables so that it will lift evenly...

Page 4: ...e common venting system 2 Visually inspect the venting system for proper size and horizontal pitch and determine there is no blockage or restriction leakage corrosion or other deficiencies which could...

Page 5: ...d with the local gas utility For temperature rise of unit see unit rating plate Condensate Drain This package unit is equipped with a 3 4 FPT coupling for condensate line connection Plumbing must conf...

Page 6: ...sure testing of that system at test pressures in excess of 1 2 PSIG 3 48kPa A1 8 N P T plugged tapping accessible for test gauge connections must be installed immediately upstream of the gas supply co...

Page 7: ...l power and control wiring to the unit waterproof type connectors must be used so that water or moisture cannot be drawn into the unit during normal operation CAUTION Compressor Units are shipped with...

Page 8: ...rt Check List After the entire control circuit has been energized and the heating section is operating make the following checks 1 Check for gas leaks using soapy solution in the unit piping as well a...

Page 9: ...correctly check manifold pressure outlet side of the gas valve It should be 10 to 10 5 w c pressure for LPG propane The furnace is designed to obtain rated input at 10 w c manifold pressure for propa...

Page 10: ...fan motor and blower motor Blower Delay Cooling The circulating air blower is controlled by a timing circuit in the integrated blower ignition control Timings are not adjustable Blower ON delay is 5 s...

Page 11: ...s the main gas valve To reset push the button on top of the switch Auxiliary Limit This control is located in the side of the circulation air blower housing The switch opens and shuts off the blower i...

Page 12: ...down the heat exchanger tubes from the flue collector end 7 If soot buildup is excessive remove the vent motor and clean the wheel and housing Run the wire brush down the flue extension at the outlet...

Page 13: ...506271 01 Page 13 of 14 Issue 0921 Wiring Diagram Single Phase Figure 8...