Section 4 Service Procedures
To reduce the risk of electric shock, fire, explosion, serious injury or death:
• Disconnect electric power to the dryer(s) before servicing.
• Close gas shut-off valve to gas dryer(s) before servicing.
• Never start the dryer(s) with any guards/panels removed.
• Whenever ground wires are removed during servicing, these ground wires must be
reconnected to ensure that the dryer is properly grounded.
W001R1
WARNING
© Copyright, Alliance Laundry Systems LLC – DO NOT COPY or TRANSMIT
b. Burner tube and igniter.
NOTE: Burner tube and igniter can be removed
without removing gas valve and bracket.
(1) Remove one screw from right side of
burner housing holding burner tube in
place. Refer to Figure 16.
(2) Gently move burner tube toward rear of
dryer to disengage tab from slot on left side
of burner housing. Refer to Figure 16.
(3) Carefully rotate burner tube and igniter
counterclockwise so tab is at 8 o’clock
position.
(4) Move air shutter end of burner tube slightly
to right and CAREFULLY remove burner
tube and igniter assembly out through front
of dryer.
To Test Gas Valve Coils:
Models starting Serial No. ________
1. Remove disconnect blocks from gas valve coils.
2. Set test meter to read OHMS and put meter
probes to terminals as follows: (Refer to
Figure 17.)
a. Holding Coil - Terminals 1 and 2 - Meter
should read 1365 ± 25 Ohms.
b. Booster Coil - Terminals 1 and 2 - Meter
should read 560 ± 25 Ohms.
c. Secondary Coil - Terminals 4 and 5 - Meter
should rear 1220 ± 50 Ohms.
Models through Serial No. ___________
1. Remove disconnect blocks from gas valve coils.
2. Set test meter to read OHMS and put meter
probes to terminals as follows.
3. Connect Ohmeter between black and blue wires
- 120 volt power supply.
a. Reading 567 to 694 Ohms - All coils are
OK.
b. Reading 1100 to 1430 Ohms - Move
Ohmeter to white and blue sensor wires.
4. Connect Ohmeter to white and blue sensor
wires.
a. Reading 1640 to 2010 Ohms - Secondary
coil open - Replace.
b. Reading 630 to 770 Ohms - Move Ohmeter
to red and black igniter wires.
5. Connect Ohmeter to red and black igniter wires.
a. Reading 540 to 660 Ohms - Hold coil open -
replace.
b. Reading 1730 to 2120 Ohms - Boost coil
open - Replace.
NOTE: If meter registers any other readings than
listed above, the respective coil should be
replaced.
Figure 17
1 - 3
4 5
D270S
TOP VIEW OF GAS VALVE
SECONDARY
COIL
HOLDING AND
BOOSTER COIL
4
5
1
2