background image

14

  

/ ALBISTONE

®

 G1 BENEFIT/G1 PLUS Skimmer Pools

Water level 
higher than  
concrete

Individual layers  
of dry concrete

Permanent  
formwork

8.

1. Lining the supporting walls and concreting around the pool shell 

Before commencing the lining and concreting works, all elements of the technology (e.g. circulation nozzles, 
pipes, fittings, etc.) must be fitted with suitable insulation – for example, MIRELON sleeves with a thickness of 
10 mm. This will insulate these components thermally, enable their thermal expansion, and protect them from 
damage during concreting.Once the preparation of the pool shell, 
technology shaft and counterflow shaft, if any, is complete, 
gradual lining of the supporting walls – which separate the 
layers of concrete and soil – can begin. The support-
ing walls (150 mm in width) can be built after the 
pool has been placed in position and its tech-
nologies have been connected. The foun-
dation slab must be suitably joined 
with the underpinning wall. When 
lining, it is important to main-
tain a sufficient distance 
(50 mm) between the 
retaining wall and the 
reinforcing elements 
of the pool shell and 
the technology shaft 
so that it is possible to 
backfill this space with 
dry concrete. Dry con-
crete must not be packed. 
This will prevents the pool shell 
from becoming uneven.

During concreting, it is necessary to con-
tinuously check the verticality (perpendicularity) 
and flatness of the walls and the identical length of the diagonals of the pool shell. In case of any deviation, 
immediately stop the concreting operation and level the shell. Concreting is carried out in layers, keeping the 
height of a single layer of concrete to a maximum of 300 mm. After each single layer of concrete is completed, 
the next layer is applied only after the previous layer has set. During concreting, it is necessary to gradually add 
water to the pool so that the water level is 100 to 200 mm higher than the layer of concrete. The part of the wa-
ter level higher than the concrete de-
pends on the plasticity of the concrete 
used. Choose a lower height of the 
water level above the concrete for dry 
concrete varieties and a higher level 
for wet concrete. Do not connect the 
pool shell to the lining firmly from the 
bottom up to the height of the shell 
reinforcing elements where these are 
located – see chapter below. Lay the 
piping during construction comple-
tion operations in perfectly packed 
sand that contains no stones or clay, 
and cover it with fine-grained sand 
that contains no clay (cover sand bed 
of at least 100 mm). It is necessary to proceed in such a way that no damage to the piping occurs e.g. by move-
ments (settling) of insufficiently packed subsoil and its surroundings, movements of frozen soil, etc. Vehicles 
must not be allowed to drive over places where the piping runs. The remaining surrounding space between the 
lining and the ground should be refilled with soil. Pack (compact) this soil carefully. 

Do not concrete the place 

where the counterflow is installed, but only refill it with packed sand.

Steel rebar  
Ø 8 mm

Dry concrete

Concreting around the pool

Summary of Contents for ALBISTONE G1 BENEFIT

Page 1: ...Skimmer pools ALBISTONE G1 BENEFIT G1 PLUS Version 12 10 2020 Update 31 07 2021 L V Preparation for construction www ALBIXON com...

Page 2: ...om 1 Contents 2 2 Surveying and Excavation 3 3 LevellingtheBottomoftheExcavationandDrainageoftheFoundationSlab 8 4 Concreting of the Foundation Slab 10 5 Notification of Readiness for Construction 11...

Page 3: ...ut of the Pool Excavation Width and Length for the Pool The width and length of the excavation for the pool for the pool placed by a crane 500 mm on each side counted from the outer dimension of the p...

Page 4: ...f the pool 4250 mm 6250 mm 8250 mm L2 foundation slab length 4700 mm 6700 mm 8700 mm L3 excavation length 5250 mm 7250 mm 9250 mm S pool width 3000 mm 2700 mm 3450 mm S1 outer width of the pool 3250 m...

Page 5: ...of the roof This is due to the need to protect the shaft from rainwater If you do not want to have the shaft elevated above the final surface level adequate drainage of rainwater must be provided aro...

Page 6: ...ewage and rainwater system on the premises This will enable the drainage pump and pool technology to be connected directly to the drainage which gives you more comfort in pool maintenance for example...

Page 7: ...ow body placed on the pool shell This is to achieve the lowest power losses The maximum distance from the exterior contour of the pool shell is 2000 mm If the counterflow is not aligned with the axis...

Page 8: ...age pump shaft serves as a sump for collecting groundwater and rainwater It must be provided with a submersible pump This pump must trigger automatically when the water level in the shaft rises and mu...

Page 9: ...olisinslopingterrain or afterbeginningtheearthworks itisfoundthatit hasaclaysubsoil whichmeansahigherprobabilityofgroundwateranditsexercisingof pressureonthepoolbody werecommendthatyouhaveageologicals...

Page 10: ...using a rebar mesh with the dimensions of 100 x 100 x 6 mm It is not necessary to reinforce the foundation slab under the technology shaft 4 Second Layer of Concrete Preparation for Final Layer Now po...

Page 11: ...s trees Choose the type of crane to order accord ing to the weight of the pool and the reach at which the pool is to be placed With great er reach required the lifting capacity of the cranes diminishe...

Page 12: ...on 4 Complete installation of the pool technology Installation of technology and its interconnection via pipes with the pool shell In order to interconnect the pool and the technology shaft correctly...

Page 13: ...you check the wall perpendicularity and flatness and the overall shape of the pool and its diagonals frequently We recommend that the shell should always be braced at the points where reinforcing ele...

Page 14: ...he diagonals of the pool shell In case of any deviation immediately stop the concreting operation and level the shell Concreting is carried out in layers keeping the height of a single layer of concre...

Page 15: ...between the edge of the shaft wall and below the cover These measures are the responsibility of the user Pipes around the technology shaft or to the service room must be laid in a sand bed with a mini...

Page 16: ...tslevelling This plate should be made of monolithic concrete reinforced with rebar mesh 100 x 100 x 6 mm The height of the base plate depends on the height of the type of paving that is chosen Make th...

Page 17: ...m Thermal insulation extruded polystyrene 30 mm Draining pipe Concrete reinforced with rebar mesh Backfill with gravel grain size 8 to 16 mm Backfill with soil Concrete Gravel Raised terrain Dry bulk...

Page 18: ...he edge Mirelon concrete paving concrete crushed aggregate edge tube permanently elastic sealant reinforcing wire slid through the edge Mirelon concrete paving concrete crushed aggregate support prism...

Page 19: ...the values and parameters specified in the report 2 Remeasuring will be carried out by an authorised person in the construction industry the parameters specified in the report are the responsibility o...

Page 20: ...n the report are the responsibility of the authorised person 3 Remeasuring will be made by the ALBIXON a s engineer this service will carry a charge of CZK 5 000 Submission of this duly completed and...

Page 21: ...west passage point gates trees The type of crane or dered according to the pool weight and the reach at which the pool is to be placed Units Units Photo documentation of the preparation for the constr...

Page 22: ...ng to the light earth strip FeZn 30x4 wire 8 mm main protective connection supply cable from the house switchboard c able for connection of filter pump and water management heat pump two cables electr...

Page 23: ...P TO 20M IF THE DISTANCE IS LONGER THE CABLE MUST BE OVERSIZED THE SUPPLY CABLE FROM THE HOUSE SWITCHBOARD TO THE TECHNOLOGY SHAFT MUST BE PROVIDED BY THE CUSTOMER BEFORE THE ORDERED COMPONENTS ARE DE...

Page 24: ...5 The heat exchanger must be connected to the main protective connection HOP Cables for electric heating n CYSY 5 J x 2 5 cable for 3kW heating and 6A 3 B circuit breaker in pool switchboard n CYSY 5...

Page 25: ...circuit breaker C16 1 KM2 heat pump contactor FA3 counterflow circuit breaker C2 1 FA4 lighting transformer circuit breaker C6 1 TR1 safety transformer 230V 12V FU1 fuse insert 2A NF1 light remote con...

Page 26: ...iltration contactor FA2 heat pump circuit breaker C16 1 FA3 lighting transformer circuit breaker C2 1 FA4 external socket breaker B16 1 TR1 safety transformer 230V 12V FU1 fuse insert 2A KT1 filtratio...

Page 27: ...aker C16 1 FA3 counterflow circuit breaker C10 3 KM2 heat pump contactor FA4 lighting transformer circuit breaker C2 1 FA5 socket breaker salt system C6 1 TR1 safety transformer 230V 12V FU1 fuse inse...

Page 28: ...n salt system and heat pump contactor KT1 salt system filtration and heat pump relay timer NF1 light remote control Xl 1 salt system power supply terminal X1 2 filtration motor power supply terminal D...

Page 29: ...ALBISTONE G1 BENEFIT G1 PLUS Skimmer Pools 29 Notes...

Page 30: ...30 ALBISTONE G1 BENEFIT G1 PLUS Skimmer Pools Notes...

Page 31: ...ALBISTONE G1 BENEFIT G1 PLUS Skimmer Pools 31 Notes...

Page 32: ...BIXON Call centre 477 07 07 11 www ALBIXON com The photographs used in this manual are for illustrative purposes only Typesetting and printing errors reserved Thank you for using the products by ALBIX...

Reviews: