COMMISSIONING
Remove the electrics panel cover to allowing access to the power supply cables
and boiler thermostat cables via the cable entry unions. Connect the cables as per
the wiring diagram (see page 21 and 22). These connections are of split type, and
will allow you to connect the phase leads to terminals L1, L2 and L3 and the
ground lead to terminal N. Connect the earth wire to the point indicated with a
grounding mark, boiler thermostats to terminal BT and the safety thermostat to
terminal ST. Then re-assemble the electric panel cover.
FUEL PUMP
FUEL HOSE CONNECTION
Fuel hose connections are made by two G1/2. threaded connections. Both
suction and return connections use the same connection types. The following
picture shows the suction and return sides of the oil pump where the oil hoses
are connected (Figure 20).
PRINCIPLE OF OPERATION
The gear set draws oil from the tank through the built-in filter and transfers it via
a valve that regulates the oil pressure to the nozzle line. Any excess fuel returns
to the tank. The pump must be free of any leakage, and bled prior to the burner's
operation.
4
1- Return
2- Internal by-pass plug
Vacuum gauge port
3-
Nozzle outlet
4- Pressure gauge port
5-
Suction
6-
Pressure adjustment
7-
3
5
Figure 20
Return
Suction
STARTING THE BURNER
To start the burner press the ON/OFF switch (Meme
1) on the control panel as shown in the picture right.
When the ON/OFF switch is on, first stage operation
of the burner begins.
To start the 2
nd
stage, that is the full rate of the
burner, the second stage switch (Meme 2) should be
pressed as well.
1
st
stage (ON/OFF switch)
2
nd
stage (Full Rate)