Airvana ipBTS C30 Installation and Commissioning, Release 4.0
1-1
Chapter 1
ipBTS system overview
This guide describes the installation and commissioning of an ipBTS™ Radio Node (RN).
•
Installation
covers all physical tasks, such as inserting modules, connecting power, and
connecting antennas. Perform the installation steps first.
•
Commissioning
covers all configuration and testing that must be performed by a
technician at the site. Commissioning is performed after installation is complete.
The ipBTS system, when used in conjunction with the ipRNC 1610, comprises part of a
Deployable BTS which provides wireless access to 1xEV-DO enabled access terminals (ATs),
PCs, and laptop computer systems.
CAUTION
This device complies with Part 24 of the FCC Rules. Changes or modifications not
expressly approved by Airvana Inc. could void the user’s authority to operate the
equipment.
This chapter describes the features and components of the ipBTS and consists of the following
sections:
•
•
•
•
Deployable BTS overview
shows a system diagram of the Deployable BTS that consists of the following
components:
•
Radio Node (ipBTS C30
) – which includes the 1xEV-DO channel card module (ADCC),
Radio module, cooling fans and filter tray.
•
Radio Node Controller
(
ipRNC 1610
) – one of the core networking elements connecting
the Radio Access Network (RAN), PSTN, and Core IP Network. Each
ipBTS connects to
the
ipRNC 1610 using backhaul link consisting of a 10/100 BaseT Ethernet interface.
Summary of Contents for ipBTS C30
Page 2: ...ii 910136 Rev01 00 Standard July 2007 ...
Page 12: ...Contents xii 910136 Rev01 00 Standard July 2007 ...
Page 20: ...About this document Notes cautions and warnings 7 910136 Rev01 00 Standard July 2007 ...
Page 30: ...Chapter 2 l Planning Requirements 2 4 910136 Rev01 00 Standard July 2007 ...
Page 68: ...Chapter 4 l RN commissioning Updating node software 4 28 910136 Rev01 00 Standard July 2007 ...
Page 72: ...Chapter 5 l RN hardware components RN shelf components 5 4 910136 Rev01 00 Standard July 2007 ...
Page 78: ...Appendix A l Radio module specifications A 6 910136 Rev01 00 Standard July 2007 ...
Page 86: ...Appendix B l RMA process B 8 910136 Rev01 00 Standard July 2007 ...
Page 89: ...Airvana ipBTS C30 Installation and Commissioning Release 4 0 Backcvr ...