![AIC N 100 WH Installation And Maintenance Manual Download Page 44](http://html1.mh-extra.com/html/aic/n-100-wh/n-100-wh_installation-and-maintenance-manual_2870754044.webp)
Fig. 15. Accessing the High and Low Voltage Terminal Strips and Electronic Board
Cascading Module
(standard from N 100 WH
Main board
Cable Hub (opt.)
Extension
modules (opt.)
x 2
x 2
I-44
Z-038791_EN • Rev A
P
roduct
I
nstallatIon
Conditions:
Tools and material:
î
Wrench, hex head, size 3
Procedure:
1.
Remove boiler front panel, see
Installing the Access Panels” on page
2.
Remove one screw. Retain for installation.
OFF
Accessing the High and Low Voltage Ter-
minal Strips and Electronic Board
Make sure that the power sup-
ply to the appliance is deactivat-
ed (power supply cable discon-
nected from the boiler) before
accessing the high voltage ter-
minal strip.
Also see
for more infor-
mation on available optional electronic components.
i
3.
Lower the main electronic casing (along with
optional extension module casing if it is in-
stalled).
4.
Release four screws and remove protective
cover. Retain hardware for reinstallation.
5.
Repeat the process for the optional exten-
sion module casing if it is installed.
6.
Proceed in the reverse order to reinstall the
protective covers and set the casings back
in position.
Follow-on tasks:
None
x 1