In the Asset Manager, verify that the test set and PC Digitizer are
configured correctly (check that the license key has been entered
correctly). Also do the following:
•
Check your system hardware connections.
•
Click the green
check- mark
button on the Asset Manager’s toolbar to
verify connectivity.
•
Return to
Server Hardware Connections
and click the
Check I/O
button to re- check it.
4
From the
FFT Analyzer
pull- down list, select
NI PCI6111- 1
(see
. Click the
Check I/O
button. A green check- mark confirms a
successful I/O check. If the I/O check is not successful, follow the same
process as in
d to verify instrument configuration and connection.
5
From the
Swept Analyzer
pull down list select
E4411A
. Click the
Check I/O
button. A green check- mark confirms a successful I/O check.
If the I/O check is not successful, follow the same process as in
to verify instrument configuration and connection.
6
Close the
Server Hardware Connections
box.
Figure 15
Select test set, FFT analyzer, and swept analyzer
E5500_server_hard_conn
05 Apr 04 rev 1
N O T E
Selecting the three instruments ties those assets to the confidence test performed in the
next step.
Summary of Contents for E5505A
Page 18: ...18 E5505A Installation Guide 1 General Information ...
Page 22: ...22 E5505A Installation Guide 2 Flat Panel Display ...
Page 30: ...30 E5505A Installation Guide 3 System Interconnections ...
Page 84: ...84 E5505A Installation Guide 6 Preventive Maintenance ...
Page 96: ...96 E5505A Installation Guide A Service Support and Safety Information ...