29
ADICOS GSME
405-2010-003 EN52
COMMISSIOnInG
6
Commissioning
NOTICE!
ADICOS systems work with electricity that may lead to system damage
and fire in the case of improper installation.
•
Prior to switching on, check that all detectors are properly mounted and
wired!
•
Commissioning may only be performed by qualified specialist personnel!
WARNING!
The protection class of the ADICOS detectors indicated in the technical data is
only ensured with a fully closed enclosure cover. on improperly closed detector
can lead to false alarms and failure.
•
Prior to commissioning, make sure that all detectors of the system are fully
closed!
ADICOS detectors must not be commissioned individually. With commissioning
of the central unit of the ADICOS system, all detectors start up automatically.
The ADICOS GSME remain in fault, until the start-up process is completed.
►
Commission the ADICOS system per the instructions of the used central unit M-Bus in
-
terface
Z
The approx. 5-minute start-up process starts automatically.
Z
The green signal LED »Operation« flashes.
Z
The yellow signal LED »Fault« illuminates continuously.
The detector remains in fault, until the end of the start-up process.
Z
The detector electronics is initiated and all sensors are sub
-
sequently heated to operating temperature.
Z
Once the start-up process is completed, the signal LED »Operation« illuminates green
continuously and the yellow signal LED »Fault« goes out.
Summary of Contents for GSME-M4
Page 40: ...12 Appendix 12 1 ADICOS mounting plate A A 1 5 0 1 5 0 1 3 0 1 3 0 6 4 A A...
Page 41: ......
Page 42: ...Appendix 40 ADICOS GSME 405 2010 003 EN52...
Page 43: ...41 ADICOS GSME 405 2010 003 EN52 Appendix...
Page 44: ......