11. To start an automatic parameter download, click Download Parameters.
12. Click Continue to confirm parameter download.
13. The SCM unit should now sound and configuration progress information appear in the log at the bottom of the window.
Note
If there is no sound from the SCM during configuration, check settings for example COM port or cables.
14. When downloading the parameters is complete, a checksum check is performed to ensure the RELIANCE IQ has received
the new parameters without fault. If the unit without fault, click OK and the unit is now ready to use.
15. Disconnect the RELIANCE IQ product cable.
16. Turn off the SCM, LPC for at least 30 seconds to fully power down the RELIANCE IQ or when no more RELIANCE IQ
products are to be configured.
17. Turn on the LPC to power up the RELIANCE IQ, for example an RGL set to flash as default, should flash.
UM-0197, Rev. 1.0, 2019/11/19
25
Copyright
©
ADB Safegate, All Rights Reserved
Summary of Contents for RELIANCE IQ L-852G(L)
Page 2: ......
Page 12: ...RELIANCE Inset Light Safety 6 Copyright ADB Safegate All Rights Reserved ...
Page 14: ...RELIANCE Inset Light About this Manual 8 Copyright ADB Safegate All Rights Reserved ...
Page 20: ...RELIANCE Inset Light Introduction 14 Copyright ADB Safegate All Rights Reserved ...
Page 50: ...RELIANCE Inset Light Spare parts 44 Copyright ADB Safegate All Rights Reserved ...
Page 51: ...UM 0197 Rev 1 0 2019 11 19 45 Copyright ADB Safegate All Rights Reserved ...
Page 52: ......