5.8 Programming RELIANCE IQ
RELIANCE IQ is delivered as a pre-programmed unit with field position information and monitor/control parameter settings.
The RELIANCE IQ can also be programmed during maintenance or updated remotely from the sub-station if installed in a
circuit using the Wake on Circuit function.
5.8.1 Hardware equipment set-up
The following hardware is required for RELIANCE IQ programming:
•
SCM – Series Circuit Modem
•
LPC – RELIANCE IQ/Sensor Interface Unit (SIU) Programming Control unit
•
Cable(s) – power and communication
•
PC – including AMT, the software maintenance toolfor programming
Connect the LPC unit to the SCM unit
The following are instructions how to set up the hardware equipment required for RELIANCE IQ programming.
Figure 1: LPC and SCM unit
Connection Box
Arbitrary wire orientation
230/240 VAC
or 100/115 VAC
Cable 5949114
Connection Box
SDM 591677
LPC 591859
LPC 1859
SCM 591677
SCM 591677
LPC 591859
Power cord
Power cord
Power cord
Disassemble/assemble EMI cable gland
with cable and make sure that
shield gets properly connected
0829F-0825M
0829F-0825M
1. Make sure the voltage selector is in the appropriate position: 120 or 240 V.
2. Connect the LPC unit to the SCM unit using the cables supplied. Connections are made at the rear of each unit.
RELIANCE Inset Light
Operation
20
Copyright
©
ADB Safegate, All Rights Reserved
Summary of Contents for RELIANCE IQ L-852G(L)
Page 2: ......
Page 12: ...RELIANCE Inset Light Safety 6 Copyright ADB Safegate All Rights Reserved ...
Page 14: ...RELIANCE Inset Light About this Manual 8 Copyright ADB Safegate All Rights Reserved ...
Page 20: ...RELIANCE Inset Light Introduction 14 Copyright ADB Safegate All Rights Reserved ...
Page 50: ...RELIANCE Inset Light Spare parts 44 Copyright ADB Safegate All Rights Reserved ...
Page 51: ...UM 0197 Rev 1 0 2019 11 19 45 Copyright ADB Safegate All Rights Reserved ...
Page 52: ......