background image

|     Installation  –   

Installing the eMH1 Wallbox on the POLEMH1

20

Remove the upper part of the housing from the 

housing base.

Connect a supply cable measuring approximately 

1.5 metres in length to the internal RCCB or termi-

nal block (basic models) of the eMH1.

 

y

To establish the connection, the grommet of the 

wallbox must be cut and the supply cable insert-

ed into the interior of the housing.

1,5 m

NOTE

Detailed information in the installation instructions

The installation instructions for the eMH1 Wallbox contain detailed information on preparing for the electrical 

connection.

Remove the right-hand grommet on the front of the 

mounting pole, use the cutter to cut an opening for 

the supply cable in the membrane of the grommet 

and then replace it.

 

y

If you also want to lay data cables into the 

wallbox, cut the left-hand grommet, too.

Using the hexagon screwdriver, screw one of the 

supplied M6×16 screws into the upper fixing point 

of the POLEMH1.

 

y

The distance between the bottom of the screw 

head and the mounting pole must be 4 mm.

4 mm

Summary of Contents for POLEMH1

Page 1: ...EN Article No 0301691_EN_b POLEMH1 POLEMH2 POLEMH3 Installation manual...

Page 2: ...de www ablmobility de Customer Service 49 0 9123 188 0 service abl de www ablmobility de en service support Revision 0301691_EN_b Version 07 03 22 Th i n k b e f o r e y o u p r i n t NOTE Please not...

Page 3: ...cations for the mechanical installation of the POLEMHx 14 Positioning the EMH9999 foundation and installing the POLEMHx 15 Specifications for the mechanical and electrical installation of the wallboxe...

Page 4: ...visit https www ablmobility de Intended use The POLEMHx mounting poles are used to install a corresponding eMH1 eMH2 or eMH3 Wallbox outdoors In order to ensure the necessary stability the POLEMHx can...

Page 5: ...e NOTE Indicates important information for operation or installation Sections marked with this symbol indicate further important information and features necessary for successful operation Actions mar...

Page 6: ...ces or the device itself must be resolved by a qualified specialist electrical contractor Should one of the following malfunctions occur please contact the specialist electrical contractor who has car...

Page 7: ...pany The wallbox installed on the POLEMHx may only be operated after it has been installed without any technical faults and subsequently approved by a qualified specialist electrical company NOTE Chan...

Page 8: ...H1 Wallbox on the POLEMH1 B These two thread points are used for directly mounting the WPR12 weather shield on the POLEMH1 see Accessories on page 13 C These six thread points are used for directly mo...

Page 9: ...x on the POLEMH2 B These two thread points are used for directly mounting the WPR12 weather shield on the POLEMH2 see Accessories on page 13 C The supply cable is inserted into the eMH2 Wallbox via th...

Page 10: ...box on the POLEMH3 B These two thread points are used for directly mounting the WPR36 weather shield on the POLEMH3 see Accessories on page 13 C The supply cable is inserted into the eMH3 Wallbox via...

Page 11: ...t this must be based on the specifications of the EMH9999 If you wish to install and operate the POLEMHx on a self made foundation a stable base and fault free oper ation outdoors cannot be guaranteed...

Page 12: ...heck the rating plate to make sure that the model you have is the mounting pole suitable for your wallbox For more information on the individual variants of the POLEMHx see the section Technical speci...

Page 13: ...ecommended Accessories The following accessories for the POLEMHx mounting poles are available separately EMH9999 Precast concrete foundation for installing the mounting pole POLEMHx h 650 mm w 430 mm...

Page 14: ...or pipe in the area in front of the foundation Suitable collision protection must be provided on site to provide the vehicle with mechanical protection from possible collisions with the POLEMHx The m...

Page 15: ...foundation The calculation design and manufacture of the self made concrete foundation are the sole responsibility of the operator or the company carrying out the installation on behalf of the operato...

Page 16: ...ng the wallbox NOTE Laying data lines If you wish to operate the wallbox in a group installation or control it in another way you will also need to lay the appropriate data cables at the installation...

Page 17: ...Smooth out the surface 9 Use the triangular key supplied to open the housing door of the POLEMHx and flip it open 10 Place the POLEMHx on the foundation and feed the power and or data cables into the...

Page 18: ...ts plus at least 50 cm Specifications for the mechanical and electrical installation of the wallboxes The mechanical and electrical installation of the wallbox on the POLEMHx must be carried out by qu...

Page 19: ...pective wallbox You can find further information in the corresponding installation instructions Installing the eMH1 Wallbox on the POLEMH1 This section describes how to install the eMH1 Wallbox on the...

Page 20: ...n in the installation instructions The installation instructions for the eMH1 Wallbox contain detailed information on preparing for the electrical connection 5 Remove the right hand grommet on the fro...

Page 21: ...H1 and hang the wallbox on the screw in the upper fixing point 8 Using the hexagon screwdriver and the two M6 16 screws supplied screw the wallbox into the two lower fixing points 9 Place the upper pa...

Page 22: ...he POLEMH2 This section describes how to install the eMH2 Wallbox on the POLEMH2 Proceed as follows 1 Open the housing cover of the wallbox with the housing cover key and put it aside 2 Loosen the scr...

Page 23: ...ed information in the installation instructions The installation instructions for the eMH2 Wallbox contain detailed information on preparing for the electrical connection 6 Remove the large grommet on...

Page 24: ...and the hexagon screwdriver to screw the wallbox into the two lower fixing points 10 Hook the housing cover onto the upper edge of the housing base and lock it using the housing cover key 11 Switch to...

Page 25: ...nstall the eMH3 Wallbox on the POLEMH3 Proceed as follows 1 Remove the large grommet on the front of the mounting pole use a cutter to cut an opening for the supply cable in the membrane of the gromme...

Page 26: ...grommets 6 Insert the individual conductors of the power sup ply cable into the respective terminals of the RCCB and tighten them using a screwdriver torque 2 5 to 3 Nm y End ferrules must be fitted o...

Page 27: ...ng pole and screw the wallbox into the mounting plate using the screwdriver and the screws supplied with the wallbox 8 Replace the electronic components cover onto the wallbox housing and fix it into...

Page 28: ...Hx The following section describes how to connect to the terminal block in the POLEMHx This process is identical for all mounting poles DANGER Dangerous electrical currents Always observe the 5 safety...

Page 29: ...ollowing connection patterns to allo cate the wires Wallbox House connection Connection pattern 1 phase TN system only for eMH1 and eMH2 Wallboxes Designation Conductor colour Marks for Phase 1 curren...

Page 30: ...it with the triangular key Safety instructions for start up and operation Before initial operation of the wallbox installed on the POLEMHx you must observe the following safety notices Ensure that the...

Page 31: ...ight switch is dirty Clean the LEDs in the head of the POLEMHx The integrated power supply unit is not connected to the supply cable Make sure the conductors that are pre fixed to the terminals are co...

Page 32: ...ate Plate metal DD11 Housing colour RAL 9011 Integrated components Terminal block 12 V power supply 2 A back up fuse 1 pole Type C on top hat rail C profile rail Lighting control 8 LEDs with integrate...

Page 33: ...Version 0301691_b last updated 23 February 2022 All rights reserved Any information contained in this manual may be changed without prior notice and does not represent any obliga tion on the part of...

Page 34: ...MADE IN GERMANY ABL GmbH Albert Bu ttner Stra e 11 91207 Lauf an der Pegnitz Germany 49 0 9123 188 0 49 0 9123 188 188 info abl de www ablmobility de...

Reviews: