Make sure that CS and TRIP output signals appear after the time delays
tCS
.
3.
Switch the operation of the zone 1 distance protection function on and fulfill all
the conditions for single-pole autoreclosing.
4.
Simulate a single phase-to-earth fault within the reach of zone 1 and both power-
swing zones.
The fault should cause a single-pole tripping with the normal operating time of
zone 1.
5.
Repeat the fault within the dead time of single-pole autoreclosing.
Make sure, that PSLPSCH generates a BLKZMUR signal and no CS and TRIP.
10.4.10.3
Checking the underreaching zone
Procedure
1.
Set the operation of all normal distance protection zones to
On
.
2.
Simulate a fault without fault resistance in the middle of distance protection zone
1.
Make sure that the trip appears within the operate time for the distance protection
zone 1 and no BLKZMOR output signal appears.
3.
Switch off the fault and prepare a new fault without fault resistance within the
normal distance protection zone 2 operate area, but outside the zone 1 operate
area.
4.
Switch on the fault and move it into the zone 1 operate area with a time delay
longer than the time set on the
tDZ
timer and faster than the time set on timer
tZL
.
5.
Observe the operate time, which must be equal to the operate time of zone 1, after
the measured impedance enters its operate area.
No delayed operation of zone 1 must be observed.
6.
Configure the STPSD functional input to connect to the START functional
output and repeat the previous fault.
Fast trip, caused by the operation of zone 1 must appear with a time delay, which
is equal to the set time delay on the timer
tZL
plus zone 1 normal operate time.
Also, observe the BLKZMOR functional output signal, which must appear for
a short time.
7.
Be sure to establish the original configuration of the IED and the original settings
of all setting parameters.
10.4.10.4
Completing the test
Continue to test another function or end the test by changing the
TestMode
setting to
Off
. Restore connections and settings to their original values, if they were changed for
testing purposes.
10.4.11
Pole slip protection PSPPPAM
Prepare the IED for verification of settings as outlined in section
and
in this chapter.
1MRK 506 355-UEN A
Section 10
Testing functionality by secondary injection
Line distance protection REL670 2.1 IEC
121
Commissioning manual
Summary of Contents for Relion 670 Series REL670
Page 1: ...Relion 670 series Line distance protection REL670 2 1 IEC Commissioning manual ...
Page 2: ......
Page 30: ...24 ...
Page 34: ...28 ...
Page 64: ...58 ...
Page 68: ...62 ...
Page 90: ...84 ...
Page 254: ...248 ...
Page 260: ...254 ...
Page 269: ...263 ...