ABB Substation Automation
Products and Systems
User’s Guide
REJ 513
1MRS750613-MUM
7
A
Operator’s instructions
1
Operation indicators
The function of the relay can be monitored with the help of three indication LEDs on
the relay front panel.
C
START
READY
TRIP
Network Partner
REJ 513
Order
No: REJ513A 402-BAA
Software No: 1MRS118012
Serial
No: ER 000001
Uaux = 110-240 Vac
Uaux = 48-220 Vdc
fn
= 50/60 Hz
In = 1/5 A (I)
REJ 513
Figure 1-1 Operation indicators
Green READY indicator
•
Indicator off:
The auxiliary voltage supply to the relay has been disconnected.
•
Lit indicator:
The relay is in normal operation, i.e. the CPU operates, no internal faults have
occurred, and auxiliary voltage is available to the relay.
•
Blinking indicator:
The internal self-supervision system has detected an internal relay fault (IRF). The
output contact of the self-supervision system operates.
Summary of Contents for REJ 513