Inverse-time characteristic
At inverse-time characteristic, the operate time is measured at two different test
current values (2 x I> and 10 x I>). The operate times thus obtained are compared
with the operate times obtained from the current/time curves of the concerned inverse-
time characteristic.
2.2.2
High-set stage I>>
Starting
Increase the test current until the relay starts and indicator L2 is lit. Then read the
start current value from the ammeter.
Operate time
Set the test current at 2 x the set start value of stage I>>. The clock is started by
closing switch S1 and stopped by closing output contact PO2.
2.3
Testing of the self-supervision system (IRF)
The self-supervision system and the function of the IRF LED and the IRF output can
be tested in the Trip test mode.
2.4
Testing of the binary input
Read the state of the binary input via SPA parameter I4. Use switch S2 to change the
state.