Prepare for commissioning
Preliminary requirements
1.
Installation engineer
Danger:
Hazardous voltage
•
Do not commission the EVSE. Only a service engineer of the
manufacturer is qualified to commission the EVSE.
Procedure
1. Tell the owner that the EVSE is ready for commissioning.
2. Make sure that the site complies with these requirements:
•
The EVSE is installed.
•
AC input power is available from the grid provider.
•
You are present during the commissioning, for assistance and to energize
the power to the EVSE on the power distribution board.
•
Internet access is available, through 2G/3G/4G or through a wired Ethernet
connection.
•
An EV must be available with a compatible connection. If the EVSE has more
than one connection type, an EV of each type must be available.
•
The site operator or owner is available to receive instructions from the
service engineer of the manufacturer.
3. Make sure that this data is available:
•
Contact data of the contact person on site
•
Address of the EVSE
•
Site name
•
Exact location of the EVSE: longitude and latitude. If there are more EVSEs
on one location, make sure that the coordinates are slightly different (at
least 0.0001 degree) so that the EVSEs are not at the same location on the
map.
•
Specification of the external fuse at the power distribution board
•
Date that the installation is done
•
Special remarks, for example to decline the authorization for the service
engineer of the manufacturer to take photos
•
Photo of the surroundings of the EVSE
Prepare for commissioning
62
9AKK107992A6488-EN | 004