ControlMaster CM10, CM30 and CM50
Universal process controllers,
1
/
8
,
1
/
4
and
1
/
2
DIN
7 Advanced Level
92
IM/CM/S–EN Rev. R
…Functions / …Bank Control
Bank Size
Select the number of stages (pumps) required for the application from
2
to
6
or
Off
.
Off
disables the
Bank Control
functionality.
Control Source
Select the analog signal that will act as the control signal for the bank control.
This is normally the Process Variable (PV) for most pump control applications.
Stage 1 (6)
Off Trip
Select the
Control Source
value (PV) at which the output (pump) will be turned off.
On Trip
Select the
Control Source
value (PV) at which the output (pump) will be turned on.
Output
Select the initial output (relay or digital output) that the output is assigned to by
default (for example, when
FIFO
or
Rotate
mode is not in operation.
Schedule
Select the wear levelling schedule required:
Off
– the output is not controlled by the bank schedule.
The state of the output is entirely controlled by its associated trip points.
FIFO
– the output is controlled according to the
FIFO
schedule mode.
Rotate
– the output is controlled according to the
Rotate
schedule mode.