Installation
46
Add/Remove
module from the
Arc Monitor or
changing configu-
ration
Warning!
Make sure that supply voltage is switched off!
To add/remove a module to the system do the steps below:
1. Remove power to the Arc Monitor.
2. Physically add/remove a module to the Arc Monitor.
3. Ensure DIP Switches are set correctly.
4. Power on.
5. Follow Start-Up sequence.
The Arc Monitor requires configuration of the system and its modules to
work.
The Human Machine Interface, HMI automatically guide the user through a
Start-Up Sequence.
Note!
For more information concerning Start-Up Sequence, See the chapter “Set-
tings” on page - 47.
Summary of Contents for Arc Guard System TVOC-2
Page 1: ...Arc Guard System TVOC 2 Installation and maintenance guide ...
Page 2: ......
Page 8: ...6 ...
Page 10: ...About Arc Guard System 8 ...
Page 54: ...Installation 52 ...
Page 74: ...Human Machine Interface functions 72 ...
Page 82: ...Technical data 80 ...
Page 89: ......