ABB VFD SUPPLEMENTAL MANUAL  

RENEWAIRE.COM 

PLANNING YOUR 
INSTALLATION

INSTALLATION

 

“ON” AND “SPEED” SIGNALS 

VFD operation in this unit is dependent on two signals: an ON signal and a SPEED (or REFERENCE) signal. 
The sources and types of these signals can vary. If the ERV is equipped with dampers the ON signal to the 
VFD comes from the end switch on the damper. If the ERV is not equipped with dampers, the ON signal 
comes from an external control connected directly to the VFD. When an ON signal is received by the VFD, 
it starts the motor. The VFD then operates the blower at the speed established by the SPEED signal. The 
SPEED signal is often provided by an external control, but in some applications “pre-set” speeds are set 
inside the VFD and are selected by external switches or relays.

PRINCIPLES OF EXTERNAL CONTROL

This ERV can be operated by various external 
control devices including remote switch or relay, 
digital time clock with relay, occupancy sensor 
with relay, and carbon dioxide sensor with relay 
and analog output. These devices are commonly 
known as 2-wire, 3-wire, and 4-wire devices. 
A Building Management System (BMS) can control 
this ERV through relay contacts and with 0-10vdc 
or 4-20mA analog inputs.

The external control devices can be connected to 
this ERV to operate each blower independently or

for one blower to act as leader and the other 
blower to act as follower. In leader-follower 
mode, a single external switch or relay calls for 
operation and the leader VFD sets SPEED to internal 
presets, or in response to an analog input signal. 
The follower VFD then operates at either exactly 
the same speed, at an offset above or below the 
leader’s speed, or at a scaled speed.  

The VFD’s are pre-programmed at the factory so 
only a few parameters need change for a 
specifi c installation.

CONNECTING EXTERNAL CONTROLS

If this ERV is equipped with damper(s), the ON signal is connected to the terminal strip in the electrical 
enclosure (“E-box”). If this ERV is not equipped with damper(s), and has 2 VFDs, the ON signal is 
connected directly to the VFDs. The SPEED signals are always connected directly to the VFD(s).

WIRE ROUTING

Route input power cables, motor cables and control 
cables separately to decrease electromagnetic 
interference caused by the rapid changes in 
the drive output voltage. Where control cables 
must cross power cables make sure that they 
are arranged at an angle as near to 90 degrees 
as possible. See the ABB VFD manual for more 
detailed wire routing instructions. 

Power cables and control cables can be brought 
into the bottom of the electrical box attached to the 
ERV unit or through the bottom of the unit itself. 
There are plugged holes to run control wires and 
power wires between the electrical box and the 
unit interior, marked on the interior of the ERV unit 
and another plugged hole in the unit compartment 
divider to run wires to VFDs in the other airstream 
compartment if needed.

In some confi gurations the VFD and/or VFD 
protective guard may need to be removed to 
access the control wire hole plug to run wires. 
A label is located in the ERV on the left interior 
wall indicating the power and control wire hole 
plug locations. Bring wires out from the top or 
bottom of the VFD mounting bracket and not 
through the mounting bracket window when 
routing wires if |the VFD is mounted over the 
hole plug.

After the wires are run, apply caulk around the 
wires at wire bushings used between the electrical 
box and ERV unit and between compartments 
in the unit to prevent air leakage between these  
compartments.

Summary of Contents for ACS320 series

Page 1: ...FD KEYPADS IN E BOX SUPPLEMENTAL MANUAL FACTORY INSTALLED ABB VARIABLE FREQUENCY DRIVES VFD IN RENEWAIRE ERV VENTILATORS RENEWAIRE COM TABLE OF CONTENTS Product info 2 Installation 3 9 Operation 10 16...

Page 2: ...al s in accordance with all applicable codes standards and licensing requirements 4 Any structural alterations necessary for installation must comply with all applicable building health and safety cod...

Page 3: ...w the leader s speed or at a scaled speed The VFD s are pre programmed at the factory so only a few parameters need change for a speci c installation CONNECTING EXTERNAL CONTROLS If this ERV is equipp...

Page 4: ...und on the Internet at www abb com drives and selecting Sales Support and Service Network Softkey Auto OFF Hand Softkey Help Key Up Down Buttons The function of each Softkey changes and is shown just...

Page 5: ...ected directly to the VFD See Fig 2 3 SPEED SIGNAL CONNECTIONS Any SPEED Signal connections are made directly to the VFD see Figures 4 6 7 The VFDs can accept 4 20mA or 0 10vdc analog control signals...

Page 6: ...9 10 11 12 15 8 7 6 5 4 3 2 1 AGND A01 AGND AI2 10V AGND AI1 SCR VFD FA 9 10 11 12 15 8 7 6 5 4 3 2 1 AGND A01 AGND AI2 10V AGND AI1 SCR VFD EA 17 19 PARAMETER SETTINGS FA VFD Parameter Setting Param...

Page 7: ...Speed Signal to the EA VFD Use shielded cable and ground the shield to Terminal 1 on either VFD 1 1 9 1 6 5 9 XVLQJ YGF 1 1 9 1 6 5 9 XVLQJ P RQQHFWLRQV IRU YGF RQWUROOHU 6HW XPSHU RU VZLWFK WR 27720...

Page 8: ...in this example since it is controlled as a Follower If it is desired that the VFDs should shut off when CO2 levels drop below a setpoint connect the Normally Open contacts of the CO2 controller term...

Page 9: ...auspices of the American Society of Heating Refrigerating and Air Conditioning Engineers ASHRAE BACnet is an American national standard a European standard a national standard in more than 30 countrie...

Page 10: ...ange the VFD parameters as required for the speci c controls system see Control Connections and VFD Parameters below for examples see also the ABB Manuals Press the AUTO switch on the keypad 230V Powe...

Page 11: ...eter 3 Press the SAVE softkey to set the Parameter to the selected value TO VIEW ONLY CHANGED VFD PARAMETERS 1 If EXIT is displayed above the left softkey press softkey repeatedly until MENU appears a...

Page 12: ...or scaling and offsetting the input to the VFD output 1302 MAXIMUM AI1 100 100 Sets maximum value for analog input Used for scaling and offsetting the input to the VFD output 1304 MINIMUM AI2 20 1 20...

Page 13: ...abb com drives SUMMARY TABLE OF COMMONLY USED PARAMETERS CONT NOTE Parameters not listed in this Table are shipped at ABB s default settings for the HVAC Application Macro Name Selection ABB HVAC Defa...

Page 14: ...NSE LEVEL is the level of measurement of indoor air quality or occupancy at which the ERV should be operating at the Design Maximum Supply Air ow Do not change PARAMETER 2003 MAX CURRENT from RenewAir...

Page 15: ...he Maximum Response Level The engineer wants the ERV to Run at a minimum of 700 CFM regardless of CO2 levels in order to control the level of indoor air pollutants generated by the furnishings Start t...

Page 16: ...value of the analog signal from the controller when CO2 600ppm 6 Set the parameters that will scale the response of the VFD to the inputs from the CO2 controller Set Parameter 1301 MINIMUM AI 1 to 55...