JOHNSON CONTROLS
SYSTEM STARTUP CHECKLIST
level should always be maintained, running or
not, above the bottom of the lower sight glass
and below the top of the upper sight glass.
If it is necessary to add oil, connect a YORK oil
pump to the charging valve on the oil separator,
but do not tighten the flare nut on the delivery
tubing. With the bottom (suction end) of the
pump submerged in oil to avoid entrance of air,
operate the pump until oil drips from the flare nut
joint, allowing the air to be expelled, and tighten
the flare nut. Open the oil charging valve on the
oil separator and pump in oil until it reaches the
proper level as described above.
6. Assure water pumps are on. Check and adjust
water pump flow rate and pressure drop across
the cooler.
Excessive flow may cause catastrophic
damage to the evaporator.
7. Check the control panel to assure it is free of
foreign material (wires, metal chips, etc.).
8. Visually inspect wiring (power and control).
Wiring MUST meet N.E.C. and local codes. See
Fig. 8 and 9, pages 35 and 36.
9. Check tightness of power wiring inside the power
panel on both sides of the motor contactors and
inside the motor terminal boxes.
10. Check for proper size fuses in main and control
circuits.
11.Verify that field wiring matches the 3-phase pow
-
er requirements of the compressor. See chiller
nameplate (Pages 25 - 26).
12. Assure 115VAC Control Power has 30A mini-
mum capacity. See Fig. 13, page 40.
13. Be certain all water temp sensors are inserted
completely in their respective wells and are
coated with heat conductive compound.
14.Assure that evaporator TXV bulbs are strapped
onto the suction lines at 4 or 8 o’clock positions.
15. Assure that the 15 ton economizer TXV bulbs
are strapped onto the compressor economizer
supply lines at 4 or 8 o’clock positions.
JOB NAME: ______________________________
SALES ORDER #: _________________________
LOCATION: ______________________________
SOLD BY: ________________________________
INSTALLING
CONTRACTOR: ___________________________
START-UP
TECHNICIAN/
COMPANY: _______________________________
START-UP DATE : _________________________
CHILLER MODEL #: _______________________
SERIAL #: _______________________________
COMPRESSOR #1
MODEL#: ________________________________
SERIAL #: _______________________________
COMPRESSOR #2
MODEL#: ________________________________
SERIAL #: _______________________________
Unit Checks (No Power)
Check the system 24 hours prior to initial start
1. Inspect the unit for shipping or installation
damage.
2. Assure that all piping has been completed.
3. Check that the unit is properly charged and that
there are no piping leaks.
4. Open each compressor suction service valve,
discharge service valve, economizer service
valve, liquid line stop valve, and oil line ball
valves.
5. The compressor oil level should be maintained
so that an oil level is visible in either of the two
oil separator sight glasses. In other words, oil
In actual operation, due to splashing,
an oil level may be seen in both sight
glasses. Run the compressor for a few
minutes, shut the system down, and
assure there is an oil level showing in
the bottom or top sight glass with the
compressor off.
Technical Data
Содержание YCAS0098EB
Страница 36: ...36 JOHNSON CONTROLS POWER AND CONTROL PANEL LAYOUTS WYE DELTA TYPICAL FIG 8 POWER PANEL SECTION 00263VIP 4...
Страница 50: ...50 JOHNSON CONTROLS This page intentionally left blank...
Страница 61: ...61 JOHNSON CONTROLS FORM 201 18 NM7 This page intentionally left blank 7...
Страница 64: ...64 JOHNSON CONTROLS Technical Data ELEMENTARY DIAGRAM FIG 18 ELEMENTARY DIAGRAM ACROSS THE LINE START...
Страница 68: ...68 JOHNSON CONTROLS Technical Data ELEMENTARY DIAGRAM FIG 21 ELEMENTARY DIAGRAM WYE DELTA START...
Страница 70: ...70 JOHNSON CONTROLS Technical Data FIG 22A CONTROL PANEL COMPONENT LOCATIONS...
Страница 71: ...71 JOHNSON CONTROLS FORM 201 18 NM7 LD03280 FIG 22B POWER PANEL COMPONENT LOCATION 7...
Страница 72: ...72 JOHNSON CONTROLS Technical Data LEGEND LD03281...
Страница 73: ...73 JOHNSON CONTROLS FORM 201 18 NM7 LD03282 LD03283 LD03284 7...
Страница 74: ...74 JOHNSON CONTROLS Technical Data CONNECTION DIAGRAM SYSTEM WIRING LD06256 LD03231 LD03232...
Страница 75: ...75 JOHNSON CONTROLS FORM 201 18 NM7 COMPRESSOR TERMINAL BOX LD03233 7...
Страница 76: ...76 JOHNSON CONTROLS LD03285 Technical Data...
Страница 77: ...77 JOHNSON CONTROLS FORM 201 18 NM7 3 4 5 6 3 4 5 6 7 8 5 6 3 4 7 8 9 10 LD06840A 7...
Страница 113: ...113 JOHNSON CONTROLS FORM 201 18 NM7 COMPRESSOR COMPONENTS CONT D FIG 40 COMPRESSOR COMPONENTS LD03669 7...
Страница 114: ...114 JOHNSON CONTROLS COMPRESSOR COMPONENTS CONT D FIG 41 COMPRESSOR COMPONENTS LD03670 Technical Data...
Страница 181: ...181 JOHNSON CONTROLS FORM 201 18 NM7 NOTES...
Страница 182: ...182 JOHNSON CONTROLS This page intentionally left blank...
Страница 183: ...183 JOHNSON CONTROLS FORM 201 18 NM7 This page intentionally left blank...