Drying Schedule
Kiln Drying Schedule
5
5-3
WMDKdoc020322
Drying Schedule
The schedules shown below will dry your timber to approximately 10%. For other end
moisture contents you should follow the following process:
1.
Select the appropriate schedule for the species and timber to be dried
2.
Follow the schedule until you reach a depression that is the equivalent of 2% MC lower
than the desired end MC (refer to the EMC Chart).
3.
Close the vent and condition the charge at the appropriate temperature.
See Table 5-2.
Schedule #1 is shown below.
See Table 5-3.
Schedule #2 is shown below.
Schedule #1
Temperature ºC
4m
3
load
6m
3
load
8m
3
load
10m
3
load
12m
3
load
Initial
32
50
75
100
125
1
1
125 means there are two outlet valves, one is 100% open (100 on the scale) and the second is 25% open (25 on the scale)
150
1º Depression
38
4
6
8
10
12
3º Depression
44
4
6
8
10
12
5.5º Depression
50
4
6
8
10
12
11º Depression
60
0
0
0
0
0
8º Depression
OFF
0
0
0
0
0
TABLE 5-2
Schedule #2
Temperature ºC
4m
3
load
6m
3
load
8m
3
load
10m
3
load
12m
3
load
Initial
32
50
75
100
125
1
1
125 means there are two outlet valves, one is 100% open (100 on the scale) and the second is 25% open (25 on the scale)
150
1º Depression
38
6
9
12
15
18
3º Depression
44
6
9
12
15
18
5.5º Depression
50
6
9
12
15
18
11º Depression
60
0
0
0
0
0
8º Depression
OFF
0
0
0
0
0
TABLE 5-3
Содержание MK20-2
Страница 50: ...Operation Loading The Kiln 4 4 5 WMDKdoc020322 Operation See Figure 4 2 FIG 4 2 Blanking Sheet Material ...
Страница 54: ...Operation Temperature Controller 4 4 9 WMDKdoc020322 Operation Set the value to 95 Press the S key again ...
Страница 68: ...SECTION 9 WMUK MODULAR KILN RECORD SHEET 0 1 2 0 1 2 0 1 2 ...
Страница 69: ... 0 1 2 0 1 2 0 1 2 ...
Страница 71: ...Replacement Parts Fan Module Assembly Replacement Parts CESHdoc020322 10 2 10 10 2 Fan Module Assembly ...