![Wood-mizer A/DH5 Скачать руководство пользователя страница 37](http://html1.mh-extra.com/html/wood-mizer/a-dh5/a-dh5_safety-setup-operation-and-maintenance-manual_994631037.webp)
SETUP & OPERATION
Stationary Sawmill Setup
SETUP & OPERATION
doc111517
2-3
2
Set up the mill on firm footing and level by eye. Fasten the mill to the floor to prevent any creep after
prolonged use. A cement pad with 5/8” (16 mm) diameter anchor bolts is recommended. The cement
pad should be rated to support 6350 lbs./sq.ft. (31 T/m) at each sawmill foot position.
NOTE:
Make sure the unit is level before securing.The sawmill mast should not be tilted from the
vertical more than 3
o
towards the log loader. The mast should not be tilted in the opposite direction.
Level the sawmill by adjusting the feet to raise or lower each end of the sawmill. Adjust all feet evenly
to avoid twisting the mill frame by jacking one feet higher than the others.
WARNING!
Do not operate a stationary sawmill without the feet
securely fastened to the floor.
See Figure 2-1.
FIG. 2-1
Содержание A/DH5
Страница 1: ...Table of Contents Section Page Table of Contents SW 07doc1115171...
Страница 2: ......
Страница 41: ...SETUP OPERATION Sawmills with cable guide SETUP OPERATION doc111517 2 7 2 FIG 2 4 LT40MRC K 7 B5 1 B0 18...
Страница 86: ...1 18 30doc111517...