User Guide
4. Part Replacement
4.9 Chassis Replacement
d.
Connect the Ethernet cable to the Ethernet port, and route the cable through each of the
baskets on the arm.
e.
Connect the SAS cables to the SAS ports, and route them through the baskets one at a
time. Make sure to follow the labels to ensure they are connected to the proper ports.
f.
Connect the power cable to the PSU and route it through each basket.
Attention:
Make sure the power cable is not connected to a PDU.
If it
is, the system will power up when the cable is connected to a PSU. This
is not intended at this stage of installation.
g.
If the installation includes more than 10 total cables, follow the recommendations in
Special Considerations for Cable Routing
, before proceeding.
Note:
Each cable must be given enough slack at the connector end
to operate smoothly. Allow 20 - 21 in. (508 – 533.4 mm) between the
connector and the first basket.
Figure 180:
Nominal Cable Length at Connectors
h.
Close all of the baskets.
i.
If the Ultrastar Data60 is being installed in a rack and will subsequently be transported
inside that rack, it is important to use the included cable tie to wrap the CMA bundle to
ensure it does not get damaged during transport. If the Ultrastar Data60 is instead being
installed where it will be operated, skip this step. Remember to remove the cable ties
after the enclosure has reached its final operational location.
j.
Reconnect the arm at the elbow to the connectors on the rail.
Step 47 :
Cable the upper CMA.
153