5.2.5 Baffle Location — 23 & 24 Tiers
Use the following baffle layouts to ensure that the discharge opening is centered to the wall sheet.
Figure 8.
23 & 24 Tiers
Page 16
- OUTLET OPENING MUST BE CENTERED
IN MIDDLE OF WALL SHEET
- BAFFLES MUST BE ORIENTED WITH NARROW
END OF OPENING FACING UP AS SHOWN
SAMPLE LAYOUT
QUANTITIES AND STARTING
LOCATION WILL VARY
PROBABLE HARDWARE
INTERFERENCE
AT HORIZONTAL SHEET OVERLAP,
REVERSE HARDWARE ORIENTATION
WITH BOLT TO INSIDE
= NO INTERFERENCE WITH BAFFLE
NORMAL HARDWARE ORIENTATION,
BOLT ON OUTSIDE
= MAJOR INTERFERENCE WITH BAFFLE
BAFFLE
INSIDE OF BIN
OUTSIDE OF BIN
HORIZONTAL WALLSHEET SEAM
MOVE RUBBER
WASHER TO
OUTSIDE
IMPORTANT: ORIENT BAFFLES WITH
NARROW END OF OPENING AT THE TOP.
CATASTROPHIC BIN FAILURE COULD
RESULT IF BAFFLES ARE INSTALLED
INCORRECTLY
Adhere to the following baffle layouts to ensure
that the discharge opening is centered to wall
sheet.
# of BAFFLES
# of BAFFLES
28
24
30
25
66
70
23 TIERS
50
78
24 TIERS
BAFFLE LOCATION - 23 & 24 TIERS
When installing baffles, the flanges on the baffles will
sometimes lay across the horizontal wall sheet seams and
come up against the protruding bolt shanks. By tightening
the baffles there will be localized interference which
pushes the wall sheet outwards at this location. When this
occurs, reverse the bolt to avoid interference.
INSTALLATION NOTES
1. For stiffened bins, 48' diameter and smaller, install
2 baffle angles (195476) per baffle as illustrated.
2. Some bins with side discharge systems must have
extra wind rings installed. Consult bin installation
manual for location and quantity of wind rings.
3. Center all sidedraw components horizontally
between uprights.
5. ASSEMBLY