WECO 5K3 LV/HV
21
1.3.3
Stack Mount
ATTENTION:
The Battery Module weighs 126.3 lb /57.3 kg and must be installed with the help of a mechanical lift, and/or
with at least two people equipped with suitable suction cups for mechanical lifting or lifting straps.
As previously stated in this manual, the 5K3 LV/HV Battery Module comes as standard in wall mount configuration.
To install in the
Stackable
configuration, the screws on the back of the battery module must be removed.
1.
Remove the back-side wall support plate using an Allen Key. The plate has five screws
.
2.
Once the wall bracket support has been removed, start stacking the second module on
top of the first module laid on the ground by using the front retractable handles.
2-Lift the second module and place it on the
first module
1-First module on the ground
platform
1
St
Module Rubber
Feet