INSTALLING THE SYSTEM
General Requirements
•
This product is intended only for installation in a restricted access location on or above a non-combustible
surface.
•
This product must be located in a controlled environment with access to crafts persons only.
•
This product is intended for installation in data centers or network telecommunication facilities (CO, vault,
hut, or other environmentally controlled electronic equipment enclosure).
•
This product is intended to be installed in a data center facility and be connected to a MESH-bonding
network (MESH-BN) or to the common bonding network in a network telecommunication facility (CO, vault,
hut, or other environmentally controlled electronic equipment enclosure).
•
This system is suitable for installation as part of the Common Bonding Network (CBN) or a data center
building MESH-bonding network (MESH-BN).
•
The installer should be familiar with the installation requirements and techniques to be used in mounting the
module mounting assembly(s) onto the mounting rails of an IT rack.
•
Rectifier module, BBU module, and module mounting assembly ventilating openings must not be blocked and
temperature of air entering these must not exceed rated operating ambient temperature range found in
SAG588706000.
•
Clearance requirements are:
a)
Recommended minimum space clearance for the front of each module mounting assembly is 80 mm (3
inches).
b)
Recommended minimum space clearance for the rear of each module mounting assembly is 80 mm (3
inches).
c)
Module mounting assemblies may be stacked together, with no space between them.
Inspecting the Equipment and Storing for Delayed Installations
Inspecting the Equipment
General
Compare the contents of the shipment with the bill of lading. Report any missing items to the carrier and your local
Vertiv Energy Systems Inc. representative immediately.
While the system is still on the truck, inspect the equipment and shipping container(s) for any signs of damage or
mishandling.
As the equipment is moved off the truck and unpacked, visually examine the system for transit damage.
Do not attempt to install the system if damage is apparent.
If any damage is noted, file a damage claim with the shipping agency within 24 hours and contact Vertiv Energy
Systems Inc. to inform them of the damage claim and the condition of the equipment.