Assembly Wide
1) Mark System Location
Locate the centerline of the system by measuring the proper offset from the roadside obstacle.
See the Drawing Package supplied with the system. Place chalk line to mark the centerline of
the system. Mark a construction line parallel to the center line and offset 6.5” [165 mm] to one
side as shown in Figure 47. The edge of the Monorail will be placed on this line.
Note:
The concrete foundation
must comply with the
project plans supplied with the system.
Warning:
Location of system with respect to the roadside obstacle is critical and
dependent on the type of Transition Panel used. See the Project Plans supplied
with the system for details.
2) Anchor the Backup
A) Concrete Backup Construction (Figure 48)
Locate Backup Face Plate using the Backup assembly drawing. Verify that any applicable
Transition Panels fit properly before anchoring the Face Plate. Drill anchor holes in the
Concrete Backup using the Face Plate as a template. Anchor the Face Plate to the
Concrete Backup using the approved adhesive anchoring system supplied with the
QuadGuard
®
(p. 12).
Warning:
Every borehole and slot in Backup and Monorail must be anchored by
a stud using an approved adhesive
.
Figure 47
(Top view of concrete foundation)
Figure 48
Anchor Backup Face Plate to Concrete Backup
FULLY CURED
CONCRETE BACKUP
BACKUP FACE PLATE
HORIZONTAL ADHESIVE KIT
WITH 3/4” X 6 1/2” STUD
Содержание QuadGuard
Страница 1: ...VALTIR QuadGuard CRASH CUSHION ASSEMBLY MANUAL PN 115348 REVISION D NOVEMBER 2022...
Страница 40: ...Valtir com 39 Revision D November 2022 Wide System Identification Figure 39 Wide Systems and Model Numbers...
Страница 65: ...Valtir com 64 Revision D November 2022 Notes...
Страница 66: ...Valtir com 65 Revision D November 2022 Notes...
Страница 67: ...Valtir com 66 Revision D November 2022 Notes...
Страница 68: ......